Hoyt Hall Renovation

February 1, 2015

July 15 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; July 22, 2016) -- Finish painting, installation of new wood trim and casework, door hardware, acoustical ceilings, fire alarm system, light fixtures; along with final plumbing, electrical and data wiring are continuing on the lower two floor levels. The overall building renovation is approximately 92 percent complete. The second and third floors are complete (excluding restroom partitions, which are currently being installed). The first floor and basement levels will be complete by July 22. A preliminary punch list has been completed for the entire building, and the general contractor is currently addressing these items. Move-in of furniture and equipment from Crane Hall has begun and will continue during July and August as individual rooms are completed in the building. Hoyt Hall is scheduled for fall semester occupancy. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place.

July 8 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; July 22, 2016) -- Finish painting, installation of new wood trim and casework, door hardware, acoustical ceilings, fire alarm system, light fixtures; along with final plumbing, electrical and data wiring are continuing on the lower two floors. The overall building renovation is approximately 90 percent complete. The second and third floors are complete (excluding restrooms). The first floor and basement levels will be complete by mid-July. Move-in of furniture and equipment from Crane Hall began on the upper two floors and will continue during July and August as spaces are completed. Hoyt Hall is scheduled for fall semester occupancy. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place.

July 1 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; scheduled substantial completion July 22, 2016) -- Finish painting, installation of new wood trim and casework, door hardware, acoustical ceilings, fire alarm system, light fixtures; along with final plumbing, electrical and data wiring are continuing on the lower two floor levels. The overall building renovation is approximately 85 percent complete. The second and third floors are complete (excluding restrooms). The first floor and basement levels will be complete by mid-July. Move-in of furniture and equipment from Crane Hall began on the upper two floors in Hoyt Hall June 17-18 and will continue during July and August as spaces are completed. Hoyt Hall is scheduled for fall semester occupancy. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place.

June 24 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; scheduled substantial completion July 22, 2016) -- Sheetrock finishing and painting; installation of new wood trim, acoustical ceilings, new fire alarm system and light fixtures; along with final plumbing, electrical and data wiring are all taking place in the building. The overall building renovation is approximately 80 percent complete. The second and third floors are complete (excluding restrooms). The first floor and basement levels will be complete by mid-July. Move-in of furniture and equipment from Crane Hall began on the upper two floors in Hoyt Hall June 17-18 and will continue during the summer as spaces in the building are completed. Hoyt Hall is scheduled for fall semester occupancy. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place.

June 17 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; scheduled substantial completion July 22, 2016) -- Sheetrock finishing, painting; installation of new wood trim, acoustical ceilings, new fire alarm system and light fixtures; along with final plumbing, electrical and data wiring are all taking place in the building. The overall building renovation is approximately 80 percent complete. The second and third floors are substantially complete (excluding restrooms). The first floor and basement levels will be substantially complete by mid-July. Move-in of furniture and equipment from Crane Hall will begin on the upper two floors in Hoyt Hall June 17-18 and continue during the summer as spaces in the building are completed. Hoyt Hall is scheduled for fall semester occupancy. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place.

June 10 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; scheduled substantial completion July 22, 2016) -- Sheetrock finishing, painting; installation of new wood trim, acoustical ceilings, new fire alarm system and light fixtures; along with rough-in of plumbing, electrical and data wiring are taking place in the basement, first and second floor levels. New carpet tile installation is complete on the second and third floors. The overall building renovation is approximately 75 percent complete. The second and third floors are substantially complete (excluding restrooms). The first floor and basement levels will be substantially complete by mid-July. Move-in of furniture and equipment from Crane Hall will begin on the upper two floors in Hoyt Hall June 17-18 and continue during the summer as spaces in the building are completed. Hoyt Hall is scheduled for fall semester occupancy. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place.

June 3 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; scheduled substantial completion July 22, 2016) -- Sheetrock finishing, painting; installation of new wood trim, acoustical ceilings, new fire alarm system and light fixtures; along with rough-in of plumbing, electrical and data wiring are taking place in the basement, first and second floor levels. New carpet tile installation is complete on the second and third floors. The overall building renovation is approximately 70 percent complete. The second and third floors are substantially complete (excluding restrooms). The first floor and basement levels will be substantially complete by mid-July. Move-in of furniture and equipment from Crane Hall will begin on the upper two floors in Hoyt Hall on June 10-11 and continue during the summer as spaces in the building are completed. Hoyt Hall is scheduled for fall semester occupancy. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place.

May 20 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; scheduled substantial completion July 22, 2016) -- Sheetrock finishing, painting; installation of new wood trim, acoustical ceilings, new fire alarm system and light fixtures; along with rough-in of plumbing, electrical and data wiring are taking place in the basement, first and second floor levels. New carpet tile installation is complete on the third floor. The overall building renovation is about 65 percent complete. The second and third floors are scheduled to be substantially complete (excluding restroom fixtures) by May 25, with the first floor and basement substantially complete by mid-July. Move-in of furniture and equipment will begin on the upper two floors in early June and continue during the summer as spaces in the building are made ready for fall semester occupancy. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place.

May 13 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; scheduled substantial completion July 22, 2016) -- Painting; installation of new door frames, acoustical ceiling grid, new fire alarm system and light fixtures; along with rough-in of electrical and data wiring are taking place throughout the building. New corridor wall framing and sheetrock installation also have been completed in the basement level. The overall building renovation is approximately 62 percent complete. The second and third floors are scheduled to be substantially complete (excluding restrooms) by May 25, with the first floor and basement substantially complete by mid-July. Move-in of furniture and equipment will begin on the upper two floors in early June and continue during the summer as spaces in the building are made ready for fall semester occupancy. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place.

May 6 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; scheduled substantial completion July 22, 2016) -- New wall construction; painting; installation of new door frames, acoustical ceiling grid, new fire alarm system and light fixtures; along with rough-in of electrical and data wiring are taking place throughout the building. Ceramic tile work is being completed in the restrooms. Plumbing rough-in on the second and third floors is complete. Building renovation is progressing from the third floor down and is about 60 percent complete. The second and third floors are scheduled to be substantially complete (excluding restrooms) by May 25, with the first floor and basement levels substantially complete by mid-July. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place.

April 22 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; scheduled substantial completion July 22, 2016) -- New wall construction; painting; installation of new door frames, acoustical ceiling grid, new fire alarm system and light fixtures; along with rough-in of electrical and data wiring are taking place throughout the building. Ceramic tile work is being completed in the restrooms. Plumbing rough-in on the second and third floors has been completed. Building renovation is progressing from the third floor down and is about 55 percent complete. The second and third floors are scheduled to be substantially complete by mid-May, with the first floor substantially complete in early June. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place.

April 15 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; scheduled substantial completion July 22, 2016) -- New wall construction; painting; installation of new door frames, acoustical ceiling grid, new fire alarm system and light fixtures; along with rough-in of electrical and data wiring are taking place throughout the building. The majority of the plumbing rough-in on the second and third floors has been completed. Building renovation is progressing from the third floor down and is about 50 percent complete. The second and third floors are scheduled to be substantially complete by mid-May, with the first floor substantially complete in early June. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place.

April 8 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; scheduled substantial completion July 22, 2016) -- New wall construction; painting; installation of new door frames, acoustical ceiling grid, new fire alarm system and light fixtures; along with rough-in of electrical and data wiring are taking place throughout the building. The majority of the plumbing rough-in on the second and third floors has been completed. Building renovation is progressing from the third floor down and is about 50 percent complete. The second and third floors are scheduled to be substantially complete by mid-May, with the first floor substantially complete in early June. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place.

April 1 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; scheduled substantial completion July 22, 2016) -- New wall construction; painting; installation of new door frames, acoustical ceiling grid, a new fire alarm system and light fixtures; along with rough-in of electrical, data wiring and plumbing are taking place throughout the building. Renovation is progressing from the third floor down and is about 47 percent complete. Self-leveling flooring underlayment work on levels one through three also is complete and ready for finish flooring installation. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place.

March 25 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; scheduled substantial completion July 22, 2016) -- New wall construction; painting; installation of new door frames, acoustical ceiling grid, a new fire alarm system and light fixtures; along with rough-in of electrical, data wiring and plumbing are taking place throughout the building. Renovation is progressing from the third floor down and is approximately 40 percent complete. Self-leveling flooring underlayment work on levels one through three also is complete and ready for finish flooring installation. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place.

March 11 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; scheduled substantial completion July 22, 2016) -- New wall construction, framing for new door openings, acoustical ceiling grid, painting, along with electrical, lighting and plumbing rough-in, are taking place. In addition, existing pneumatic zone control valves are being replaced on all fin-tube radiators with new direct digital control units. Renovation in the building is progressing from the third floor down and is approximately 35 percent complete. Flooring underlay work in the third floor has begun. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place.

March 4 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; anticipated substantial completion July 22, 2016) -- New wall layout, framing for new door openings, acoustical ceiling grid, painting, along with electrical, lighting and plumbing rough-in, are taking place. In addition, existing pneumatic zone control valves are being replaced on all fin-tube radiators with new direct digital control units. Renovation in the building is progressing from the third floor down and is about 30 percent complete. Interior stud wall framing has begun throughout the building. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place.

February 26 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; anticipated substantial completion July 22, 2016) -- New wall layout, framing for new door openings, acoustical ceiling grid, painting, along with electrical, lighting and plumbing rough-in, are taking place. In addition, existing pneumatic zone control valves are being replaced on all fin-tube radiators with new direct digital control units. Renovation in the building is progressing from the third floor down and is about 25 percent complete. Interior stud wall framing in the basement level and floor preparation will begin in the next few weeks. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place.

February 19 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; anticipated substantial completion July 22, 2016) -- The majority of miscellaneous demolition work has been completed. New wall layout, framing for new door openings, paint preparation, along with electrical and plumbing rough-in, are taking place. In addition, existing pneumatic zone control valves are being replaced on all fin-tube radiators with new direct digital control units. Renovation in the building is progressing from the third floor down and is approximately 20 percent complete. Interior stud wall framing in the basement level and floor preparation will begin later this month. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place.

February 12 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; anticipated substantial completion July 22, 2016) -- The majority of miscellaneous demolition work is complete inside the building. New wall layout, framing for new door openings, paint preparation, along with electrical and plumbing rough-in, are taking place. In addition, existing pneumatic zone control valves are being replaced on all fin-tube radiators with new direct digital control units. Renovation is progressing from the third floor down. Interior stud wall framing in the basement level will begin later this month. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place.

February 5 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; anticipated substantial completion July 22, 2016) -- The majority of miscellaneous demolition work is complete inside the building. New wall layout, framing for new door openings, paint preparation, along with electrical and plumbing rough-in, are taking place. In addition, existing pneumatic zone control valves are being replaced on all fin-tube radiators with new direct digital control (DDC) units. The renovation work in the building is progressing from the third floor down. Interior stud wall framing in the basement level will begin later this month. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place.

January 29 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; anticipated substantial completion July 22, 2016) -- The majority of miscellaneous demolition work is complete inside the building. New wall layout, paint preparation, electrical and plumbing rough-in have begun and are ongoing. Renovation work in the building is progressing from the third floor down. Interior stud wall framing in the basement level and other areas of the building will start in February. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place.

January 22 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; anticipated substantial completion July 22, 2016) -- The majority of miscellaneous demolition work is now complete inside the building. Electrical and plumbing rough-in have begun. Interior stud wall framing in the basement level and other areas of the building will start in February. The shop drawing/submittal review process is still ongoing. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place inside.

January 15 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; anticipated substantial completion July 22, 2016) -- Required structural repairs to the lower level of Hoyt Hall have been completed. The general contractor for the renovation project (Elk Ridge) has mobilized on site, and work in Hoyt Hall has begun. Miscellaneous demolition by all construction trades is taking place. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place inside.

January 8 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; anticipated substantial completion July 22, 2016) -- Required structural repairs to the lower level of Hoyt Hall have been completed. The general contractor for the renovation project (Elk Ridge) has mobilized on site, and work in Hoyt Hall has begun. Miscellaneous demolition by all construction trades is taking place. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place inside.

December 18 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; anticipated substantial completion July 22, 2016) -- The next Owner/Architect/Contractor (OAC) meeting has been rescheduled for Wednesday, Dec. 23. The shop drawing/submittal and review process also is taking place. Required structural repairs to the lower level of Hoyt Hall are nearing completion and are being performed under a separate contract managed by the UW Physical Plant. The general contractor for the renovation project (Elk Ridge) has mobilized on site and work in Hoyt Hall has begun. Work also will occur over the holiday break. A designated contractor parking area has been established on the west side of the building. The Hoyt Hall Renovation work is expected to be substantially complete by July 22, 2016. Please observe all temporary barricades, construction fencing, cautionary signs or other posted instructions around the building where work is taking place inside.

December 18 Update. Hoyt Hall (UW Physical Plant, Arcon Inc.; December 2015) -- Repairs to the basement 1915 and 1921 portions of the interior steel frame structure are complete. Punch list items and cleanup are ongoing. Staging will be north of the building and south of Student Health. Access to the building is restricted. Please use caution around crews and equipment.

December 11 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; anticipated substantial completion July 22, 2016) -- An initial pre-construction meeting and walk-through of the building with the design and construction teams took place Friday, Nov. 6. The next Owner/Architect/Contractor (OAC) meeting is scheduled Wednesday, Dec. 16. The shop drawing/submittal process is well underway. Required structural repairs to the lower level of Hoyt Hall are approximately 95 percent complete and are being performed under a separate contract managed by the UW Physical Plant. Physical renovation work in Hoyt Hall has begun and will be substantially complete by July 22, 2016. Please observe all temporary barricades, cautionary signs or other posted instructions around the building where work is taking place inside.

December 11 Update. Hoyt Hall (UW Physical Plant, Arcon Inc.; December 2015) -- Repairs to the basement 1915 and 1921 portions of the interior steel frame structure are nearing completion. Wall demolition, floor repair and wall patching will be ongoing. Staging will be north of the building and south of Student Health. Access to the building is restricted. Please use caution around crews and equipment.

December 4 Update. Hoyt Hall Renovation (General contractor Elk Ridge Builders & Design LLC, Laramie; anticipated substantial completion July 22, 2016) -- An initial pre-construction meeting and walk-through of the building with the design and construction teams took place Friday, Nov. 6. A second pre-construction meeting will take place Wednesday, Dec. 9, prior to site mobilization on the site. The shop drawing/submittal process has begun and is well underway. Required structural repairs to the lower level of Hoyt Hall are approximately 85 percent complete and are being performed under a separate contract managed by the UW Physical Plant. Physical renovation work in Hoyt Hall will begin during the week of Dec. 14, and be substantially complete by July 22, 2016. Please observe all temporary barricades, cautionary signs or other posted instructions around the building where work is taking place inside.

December 4 Update. Hoyt Hall (UW Physical Plant, Arcon Inc.; December 2015) -- Repairs to the basement 1915 and 1921 portions of the interior steel frame structure are nearing completion. Wall demolition, floor repair and wall patching will be ongoing. Staging will be north of the building and south of Student Health. Access to the building is restricted. Please use caution around crews and equipment.

November 20 Update. Hoyt Hall Renovation (Elk Ridge Builders & Design LLC, Laramie; anticipated substantial completion July 22, 2016) -- An initial pre-construction meeting and walk-through of the building with the design and construction teams took place Friday, Nov. 6. A second pre-construction meeting prior to site mobilization will be scheduled in early December. The shop drawing/submittal process has begun and will be completed over the next two months. Required structural repairs to the lower level of Hoyt Hall are approximately 70 percent complete at this time and are being performed under a separate contract managed by the UW Physical Plant. Physical renovation work in Hoyt Hall will begin in mid-December, after all the structural repairs are finished, and be substantially complete by July 22, 2016. Please observe all temporary barricades, cautionary signs or other posted instructions around the building where work is taking place inside.

November 20 Update. Hoyt Hall (UW Physical Plant, Arcon Inc.; December 2015) -- Repairs to the basement 1915 and 1921 portions of the interior steel frame structure are nearing completion. Wall demolition, floor repair and wall patching will be ongoing. Staging will be north of the building and south of Student Health. Access to the building is restricted. Please use caution around crews and equipment.

November 13 Update. Hoyt Hall Renovation (Elk Ridge Builders & Design LLC, Laramie; anticipated substantial completion July 22, 2016) -- A pre-construction meeting and walk-through of the building with the design and construction teams took place Friday, Nov. 6. The shop drawing and submittal process will be expedited over the next two months before the start of construction. Required structural repairs to the lower level of Hoyt Hall are approximately 50 percent complete and being done under a separate contract managed by the UW Physical Plant. Physical renovation work in Hoyt Hall will begin in mid-December, after all the structural repairs are finished, and be substantially complete by July 22, 2016. Please observe all temporary barricades, cautionary signs or other posted instructions around the building where work is taking place inside.

November 13 Update. Hoyt Hall (UW Physical Plant, Arcon Inc.; November 2015) -- Repairs to the basement interior steel frame structure are in progress. Staging will be north of the building and south of Student Health. Access to the building is restricted. Please use caution around crews and equipment.

November 6 Update. Hoyt Hall Renovation (Elk Ridge Builders & Design LLC, Laramie; anticipated substantial completion July 22, 2016) -- An agreement with the selected general contractor is being finalized, and a pre-construction meeting is scheduled Friday, Nov. 6. Required structural repairs to the lower level of Hoyt Hall are being completed under a separate contract managed by the UW Physical Plant. Renovation work in the building will begin in mid-December, after all the structural repairs are finished, and be substantially complete by July 22, 2016. Please observe all temporary barricades, cautionary signs or other posted instructions around the building where work is taking place inside.

November 6 Update. Hoyt Hall (UW Physical Plant, Arcon Inc.; November 2015) -- Repairs to the basement interior steel frame structure are in progress. Staging will be north of the building and south of Student Health. Access to the building is restricted. Please use caution around crews and equipment.

October 30 Update. Hoyt Hall Renovation (Elk Ridge Builders & Design LLC, Laramie; anticipated completion July 22, 2016) -- An agreement with the selected general contractor is being finalized, and a pre-construction meeting is planned for Friday, Nov. 6. Required structural repairs to the lower level of Hoyt Hall are being completed under a separate contract managed by the UW Physical Plant. Renovation of the building is anticipated to begin in mid- to late December, after all the structural repairs are finished, and be substantially complete by July 22, 2016. Please observe all temporary barricades, cautionary signs or other posted instructions around the building where work is taking place inside.

October 30 Update. Hoyt Hall (UW Physical Plant, Arcon Inc.; October 2015) -- Repairs to the basement interior steel frame structure are in progress. Staging will be north of the building and south of Student Health. Access to the building is restricted. Please use caution around crews and equipment.

October 23 Update. Hoyt Hall Renovation (Elk Ridge Builders & Design LLC, Laramie; anticipated completion July 22, 2016) -- An agreement with the selected general contractor is being prepared, and a pre-construction meeting will be scheduled in the next few weeks. Required structural repairs to the lower level of Hoyt Hall are being completed under a separate contract managed by the UW Physical Plant. Renovation of the building is anticipated to begin in early January 2016, after all the structural repairs are finished, and be substantially complete by July 22, 2016. Please observe all temporary barricades, cautionary signs or other posted instructions around the building where work is taking place inside.

October 23 Update. Hoyt Hall (UW Physical Plant, Arcon Inc.; October 2015) -- Repairs to the basement interior steel frame structure are in progress. Staging will be north of the building and south of Student Health. Access to the building is restricted. Please use caution around crews and equipment.

October 18 Update. Hoyt Hall Renovation (General contractor TBD, anticipated completion July 22, 2016) -- Bids were received from four resident contractors Thursday, Oct. 1. The recommendation for the construction contract has been approved by the Board of Trustees, and negotiations with the contractor will begin soon. Required structural repairs to the lower level of Hoyt Hall are being completed under a separate contract managed by the UW Physical Plant. Renovation of the building is anticipated to begin in early January 2016, after all the structural repairs are finished, and be substantially complete by July 22, 2016. Please observe all temporary barricades, cautionary signs or other posted instructions around the building where work is taking place inside.

October 18 Update. Hoyt Hall (UW Physical Plant, Arcon Inc.; October 2015) -- Repairs to the basement interior steel frame structure are in progress. Staging will be north of the building and south of Student Health. Access to the building is restricted. Please use caution around crews and equipment.

October 11 Update.  Hoyt Hall Renovation (General contractor TBD, anticipated completion July 22, 2016) -- Bids were received from four resident contractors Thursday, Oct. 1. A recommendation for the construction contract has been forwarded to the Board of Trustees. Required structural repairs to the lower level of Hoyt Hall are currently being completed under a separate contract managed by the UW Physical Plant. The renovation of the building is anticipated to begin in early January 2016, after all the structural repairs are finished, and be substantially complete by July 22, 2016. Please observe all temporary barricades, cautionary signs or other posted instructions around the building where work is taking place inside.

October 4 Update.  Hoyt Hall Renovation (General contractor TBD, anticipated completion Oct. 28, 2016) -- The bid date for this project is scheduled for Thursday, Oct. 1, 2015. Required structural repairs to the lower level of Hoyt Hall are currently being completed under a separate contract managed by the UW Physical Plant. The renovation work in the building is currently anticipated to begin in early January 2016, after all the structural repairs have been completed. Please observe all temporary barricades, cautionary signs or other posted instructions around the building where work is taking place inside.

September 27 Update. Hoyt Hall (UW Physical Plant, Arcon Inc.; October 2015) -- Repairs to the basement interior steel frame structure are in demolition stages. Staging will be north of the building and south of Student Health.  Access to the building is restricted. Please use caution around crews and equipment.

September 20 Update. Hoyt Hall Renovation (General contractor TBD, anticipated completion fall/winter 2016) -- The bid date for this project has been rescheduled for Thursday, Oct. 1, 2015. A second pre-bid meeting with interested contractors is scheduled for Thursday, Sept. 24, to clarify changes in project scope and schedule requirements. Required structural repairs to the lower level of Hoyt Hall are being completed under a separate contract managed by the UW Physical Plant. The renovation work in the building is currently anticipated to begin in early January 2016, after all the structural repairs have been completed. Please observe all temporary barricades, cautionary signs or other posted instructions in areas of the building where work is taking place.

September 13 Update. Hoyt Hall Renovation (General contractor TBD, anticipated completion fall/winter 2016) -- The bid date for this project has been rescheduled for Thursday, Oct. 1, 2015. A second pre-bid meeting with interested contractors is scheduled Thursday, Sept. 24, to clarify changes in project scope and schedule requirements. Required structural repairs to the lower level of Hoyt Hall will be completed under a separate contract managed by the UW Physical Plant. The renovation work in the building is currently anticipated to begin in early January 2016, after all the structural repairs are complete. Please observe all temporary barricades, cautionary signs or other posted instructions in areas of the building where work is taking place.

September 6 Update. Hoyt Hall Renovation (General contractor TBD, anticipated completion summer 2016) -- A new bid date for this project has been scheduled for Thursday, Oct. 1, 2015. A second pre-bid meeting with interested contractors is scheduled for Thursday, Sept. 24, to clarify changes in project scope and schedule requirements. Required structural repairs to the lower level of Hoyt Hall are being completed under a separate contract managed by the UW Physical Plant. It is anticipated that the structural repairs work will be completed in both the south and central portions of the building by mid-November and in the north portion by mid-December. Please observe all temporary barricades, cautionary signs or other posted instructions in areas of the building where work is taking place.

August 30 Update. Hoyt Hall Renovation (General contractor TBD) -- Due to structural repairs that need to be made to the lower level of the building under a separate contract, the bid date for the Hoyt Hall renovation has been postponed. After the full extent of the structural repair work is known, a new bid date and completion schedule will be established.

August 23 Update. Hoyt Hall Renovation (General contractor TBD) -- Due to structural repairs that need to be made to the lower level of the building under a separate contract, the bid date for the Hoyt Hall renovation has been postponed. After the full extent of the structural repair work is known, a new bid date and completion schedule will be established.

August 16 Update. Hoyt Hall Renovation (General contractor TBD; scheduled completion April 2016) -- This project is currently out for competitive bidding with an established bid date of Thursday, Aug. 27. A pre-bid meeting with interested contractors is scheduled for Monday, Aug. 17. After a construction contract has been approved, the Hoyt Hall renovation work is expected to begin by Oct. 1 and be substantially complete by April 29, 2016.

August 9 Update. Hoyt Hall Renovation (General contractor TBD; scheduled completion April 2016) -- This project is currently out for competitive bidding with an established bid date of Thursday, Aug. 27. A pre-bid meeting with interested contractors is scheduled for Aug. 17. After a construction contract has been approved, the Hoyt Hall renovation work is expected to begin by Oct. 1 and be substantially complete by April 29, 2016. All abatement work inside the building is complete.

August 2 Update. Hoyt Hall Renovation (General contractor TBD; scheduled completion April 2016) -- This project is currently out for competitive bidding with an established bid date of Thursday, Aug. 27, 2015. A pre-bid meeting with interested contractors is scheduled for Aug. 17. After a construction contract has been approved, the Hoyt Hall renovation work is expected to begin by Oct. 1, 2015, and be substantially complete by April 29, 2016. All abatement work inside the building is complete.

July 26 Update. Hoyt Hall Renovation (General contractor TBD, projected bid date is Thursday, Aug. 27, to allow for significant changes to electrical/data wiring upgrades) -- Occupants of Hoyt Hall are being moved temporarily into Crane Hall for the fall 2015 and spring 2016 semesters while extensive renovations take place in Hoyt Hall. Colorado Hazard Control is nearing completion of abatement work in the building, and work is approximately 75 percent complete. The remaining abatement should be complete by July 24. Renovation of Hoyt Hall is expected to begin by Oct. 1 and be substantially complete April 29, 2016. Please observe temporary barricades, cautionary signs or other posted instructions in areas where work is taking place.

July 19 Update. Hoyt Hall Renovation (General contractor TBD, projected bid date has been extended to Thursday, August 27, to allow for significant changes to electrical/data wiring upgrades) -- Occupants of Hoyt Hall are being temporarily moved into Crane Hall for the fall 2015 and spring 2016 semesters while extensive renovations take place in Hoyt Hall. Colorado Hazard Control is currently completing abatement work in the building and work is approximately 75 percent complete. The remaining abatement should be complete by July 24. The renovation work in Hoyt Hall is expected to begin by October 1, 2015, and be substantially complete April 29, 2016. Please observe temporary barricades, cautionary signs or other posted instructions in areas where work is taking place.

July 12 Update. Hoyt Hall Renovation (General contractor TBD, projected bid date is Thursday, Aug. 20) -- Occupants of Hoyt Hall who have been moved to the Guthrie House (former UW Foundation building) this summer will be moved into Crane Hall beginning July 15 for the fall 2015 and spring 2016 semesters while extensive renovation takes place in the building. Colorado Hazard Control is completing abatement work in the building and is approximately 60 percent complete. The remaining abatement is expected to take another two weeks. Please observe temporary barricades, cautionary signs or other posted instructions in areas where work is taking place.

June 28 Update. Hoyt Hall Renovation (General contractor TBD, projected bid date is Thursday, Aug. 20) -- Occupants of Hoyt Hall have been moved to the Guthrie House (former UW Foundation building) this summer and to Crane Hall for the fall 2015 and spring 2016 semesters while extensive renovation takes place in the building. Colorado Hazard Control is currently completing abatement work in the building; this work will last for several weeks. Please observe temporary barricades, cautionary signs or other posted instructions in areas where work is taking place.

June 21 Update. Hoyt Hall Renovation (General contractor TBD, projected bid date is Tuesday, Aug. 18) -- Occupants of Hoyt Hall are being moved to the Guthrie House (former UW Foundation building) this summer and to Crane Hall for the fall 2015 and spring 2016 semesters while extensive renovation takes place in the building. Colorado Hazard Control has completed abatement work in Rooms 112 and 114. The remaining abatement in the building will begin Monday, June 22, and last several weeks. Please observe temporary barricades, cautionary signs or other posted instructions in areas where work is taking place.

June 14 Update. Hoyt Hall Renovation (General contractor TBD, projected bid date is Tuesday, Aug. 18) -- Occupants of Hoyt Hall are being moved to the Guthrie House (former UW Foundation building) this summer and to Crane and Hill halls for the fall 2015 and spring 2016 semesters while extensive renovation takes place in the building. Colorado Hazard Control has begun abatement work in Rooms 112 and 114. The remaining abatement in the building will begin Monday, June 22, and last several weeks.

June 7 Update. Hoyt Hall Renovation (General contractor TBD, projected bid date is Aug. 18, 2015) -- Occupants of Hoyt Hall are being moved to the Guthrie House (former UW Foundation building) this summer and to Crane and Hill halls for the fall 2015 and spring 2016 semesters while extensive renovation takes place in the building. Colorado Hazard Control will start abatement work in Room 112 on Wednesday, June 10. The remaining abatement in the building will begin on Monday, June 22, and last several weeks.

There are presently waste and metal recycling dumpsters located at the service drive on the northeast corner of Hoyt Hall. These are being used to dispose of unwanted items from the building. Interior renovation work on Hoyt Hall is expected to begin in late September and be substantially complete in April 2016.

Contact Us

Administration

Find us on Facebook (Link opens a new window) Find us on YouTube (Link opens a new window)

1000 E. University Ave. Laramie, WY 82071
UW Operators (307) 766-1121 | Contact Us | Download Adobe Reader

Twitter Icon Youtube Icon Instagram Icon Facebook Icon

Accreditation | Virtual Tour | Emergency Preparedness | Employment at UW | Gainful Employment | Privacy Policy | Harassment & Discrimination | Accessibility Accessibility information icon