Some of the content on this website requires JavaScript to be enabled in your web browser to function as intended. While the website is still usable without JavaScript, it should be enabled to enjoy the full interactive experience.

Skip to Main Navigation. Each navigation link will open a list of sub navigation links.

Skip to Main Content

Renovation Information|Campus Recreation
 
Interior Design Plans

Interior Design Plans Draft (2.3MB)

Contact Us

Campus Recreation
Half Acre Gym
Dept. 3604
1000 E. University Ave.
Laramie, WY 82071
Phone: (307) 766-3370
Fax: (307) 766-6720
Email: rec@uwyo.edu
Find us on Facebook (Link opens a new window)
Half Acre, More Than a Gym

Construction of the renovation and expansion of Half Acre Gym is underway.  The project will be accomplished in two phases, allowing patrons to utilize portions of the facility throughout the entire process.  During the renovation and expansion project, we will update our patrons with the most accurate and timely information possible.  Please check this web site and signage throughout the facility for updates on this project.

News and Events

Campus Construction Update for June 28 - July 11

Half Acre Gymnasium Addition and Renovation (General contractor Groathouse Construction, Inc., Cody; Phase I east reconstruction/addition was substantially completed March 13, 2015; Phase II, historic west renovation, summer 2015).

Phase I of the Half Acre Recreation and Wellness Center opened on Monday, March 16. Punch-list tasks, building technology and transitional work toward Phase II renovation will continue post-occupancy.  Pedestrian access to the new south building entrance from Prexy's Pasture and from the east Wyoming Union parking lot has reopened. Please observe temporary barricades, cautionary signage or other posted instructions in areas where work will continue. 

The west historic entrance is closed for Phase II renovation. Additional construction and staging areas are being established.  Phase II deconstruction activities are complete, and renovation preparatory work is nearing completion on the first floor, including remedial structural and floor slab construction.  Renovation is underway throughout Phase II, including mechanical and electrical rough-in, running track structure and floor alterations, new pool plumbing and the new whirlpool feature is slated to begin in early July.  Completion of Phase II renovation is now scheduled for fall 2015. 

Construction and staging areas north, east and west of the existing building have been established and are closed to all vehicular and pedestrian traffic, except that which is construction related.  Pedestrian pathways north and south of Half Acre Gym remain open; however, the continuing construction activities in this vicinity will result in increased congestion.  Temporary traffic controls, barricades and signs will be established as needed by specific site activities.  Please observe all posted traffic control, construction signs and temporary flagging in the affected areas.