Campus Construction Update for Week of Jan. 22

January 20, 2012

These are among the construction activities scheduled Jan. 22-28 at the University of Wyoming.

The UW Facilities Planning Office reports the following activities for the week:

Visual Arts Building (22nd St. and Willett Drive near the Centennial Complex) -- Spring semester classes began Jan. 9. Be aware that there will be traffic and activities throughout the site as final furniture is received; remaining items are being moved into the building and the contractor is completing touch-up work. The contractor's office and a small crew will remain on site through the next several weeks.

A&S Auditorium (Scheduled completion, this March) -- The project focuses on adding wheelchair access from the seating area to the stage. Drywall finishing and electrical work are scheduled this week. Handrails are complete. The auditorium will be available for scheduled performances.

Ivinson Parking Lot Expansion -- Due to frozen ground, the backfill of the old Ivinson Building will begin in the spring along with the parking lot expansion work. Fifteen pre-existing parking spaces are now open with access off 11th Street.

Student Apartments Bison Run Village (Scheduled completion August 2012) -- The new apartments are in a three-block area south of Willett Drive between Crane and Soule streets. Apartment framing, electrical/plumbing rough-ins and insulation installation continue. Drywall installation has begun. The community center is 95 percent complete with a February completion date. There will be a total of 15 apartment buildings (332 beds) with a community center and maintenance building.

Energy Innovation Center (formerly called the Energy Resources Center, at 1020 Lewis St., scheduled completion September, 2012) -- Access to main campus will be between or through Earth Sciences and the Berry Center. Lewis Street will remain closed during construction. Parking will be limited in areas around construction, including the drive along the west side of Engineering. The access from main campus along the west side of Engineering to Lewis Street will be closed during this phase of construction. The west end of the ramp behind Engineering will be closed. Handicapped parking has been relocated to the northwest corner of Lewis and 10th streets, with access through the Berry Center or Earth Sciences to main campus. Minor concrete work at foundations on the west and floor slab pours will continue throughout the week. There will be work on underground utilities throughout the site as foundation and steel erection allow. Backfill at foundations will continue as foundation work allows. There will be construction traffic for delivery of materials throughout the week. Expect congestion from deliveries. Framing of interior walls will continue. Take extreme care when walking around trucks waiting in the street.

The UW Physical Plant reports the following activities for the week. Please direct questions to the service desk, 766-6225.  

Notice: Snow and ice removal will occur as needed throughout the winter. Please use caution around snow removal equipment and be safe walking, riding and driving on the snow. There is no parking from 2-6 a.m. in the tow-away zone on the south side of Lewis Street to allow for snow and ice removal. Report ice spots to the Physical Plant service desk.

Campus -- The well pump in the parking lot west of Fine Arts will be replaced beginning Monday. Barricades will be placed around the work area.

Agriculture Building -- Painting of the restrooms throughout the building is complete.

Animal Science -- Painting in the east hallways continues. Please use caution around work areas.

Knight Hall -- Carpet replacement and painting is ongoing throughout the building this week. Please use caution in these areas.

East Shuttle Lot (30th Street and Willett Drive) -- Bus shelter relocations are on hold until the new shelters arrive.

Find us on Instagram (Link opens a new window)Find us on Facebook (Link opens a new window)Find us on Twitter (Link opens a new window)Find us on LinkedIn (Link opens a new window)Find us on YouTube (Link opens a new window)