Campus Construction Update for Week of July 22

July 20, 2012
Construction worker standing on roof
A worker takes measurements at the Honors Center at 10th and Ivinson streets. Sidewalks around the house are closed.

These are among the construction activities scheduled July 22-28 at the University of Wyoming:

The UW Facilities Planning Office reports the following activities for the week:

Landscape Projects -- Construction work has begun on Sullivan Plaza, Public Edge Practice Field, Public Edge Southwest Campus Entry Marker and Bureau of Mines Landscape, and will continue during the summer months.

Sullivan Plaza -- Access to the south entrances of the Education Building and surrounding pedestrian pathways will be restricted by construction through Aug. 24. Plaza pedestrian paving, stone and boulder setting, and reconstruction of the front entry stairs is ongoing. A portion of the parking area north of Wyoming Hall will be barricaded through July 20 for construction staging purposes.

Public Edge Practice Field (Tailgate Park) -- 20th Street adjacent to the field, as well as adjacent portions of 20th Street and Grand Avenue pedestrian sidewalks, will be temporarily closed by construction through July 30. Construction may limit westbound Grand Avenue to a single lane at times. Boulder setting, fencing and general landscaping is ongoing.

Public Edge Southwest Campus Entry Marker -- Adjacent portions of Ninth Street and Grand Avenue pedestrian sidewalks may be temporarily closed by construction through Sept. 28. Earthwork will begin the week of July 22.

Bureau of Mines Landscape -- The vehicular access and pedestrian corridor between the Berry Biodiversity Conservation Center and the Health Sciences Center may be restricted by construction through Aug. 24. General landscaping work will begin the week of July 22.

Counselor Education Training Clinic (Education Building, scheduled completion Oct. 22) -- Renovation construction work in the northeast portion of the basement of the Education Building is under way. Demolition activities will predominate through July 27, with general renovation construction following. Construction staging will restrict access via the northeast building entry and to a portion of the parking area northeast of the Education Building through completion of the renovation project.

Museum Closed -- The UW Geological Museum is closed for renovation and is scheduled to reopen at the beginning of the fall semester.

Ivinson Parking Lot Expansion -- Final subgrading is nearly complete. Concrete curb and gutter continues. Expect heavy truck traffic on 10th and 11th streets. This affects 31 parking spaces during construction. The project will add 67 additional parking spaces.

Student Apartments Bison Run Village (Scheduled completion August 2012) -- The new apartments are in a three-block area south of Willett Drive between Crane and Landmark Village. The community center and apartment model unit are now open Mondays through Fridays. Residence Life and Dining Services maintenance staff members have moved into the community center's maintenance area. All of the apartment buildings are now complete, with punch-list work ongoing. Landscaping continues on all parts of the site. Exterior punch lists will be issued this week. There are a total of 15 apartment buildings (332 beds) with the community center and maintenance building.

White Hall Renovations -- Renovation and abatement work is ongoing. Abatement is proceeding from top floors to bottom floors and is 75 percent complete. Electrical and renovation demolition continues on the eighth through 12th floors. The west parking lot will be closed until summer 2013. Underground electrical excavation continues in front of Washakie. This will affect half of the sidewalk and partial access into Washakie. Pedestrian traffic will need to use caution.

Energy Innovation Center (formerly ERC, at 1020 Lewis St., scheduled completion September 2012) -- Access to main campus will be between or through Earth Sciences and the Berry Center. Lewis Street will remain closed during construction. Parking will be limited in areas around construction, including the drive along the west side of Engineering. The access from main campus, along the west side of Engineering to Lewis Street, will be closed during this phase of construction. The west end of the ramp, behind Engineering, will be closed. Handicapped parking has been relocated to the northwest corner of Lewis and 10th streets, with access through the Berry Center or Earth Sciences Building to main campus.

Framing of interior walls is complete, along with drywall in most areas. Painting is well under way, along with other interior finishes. Interior door and window frames are under way in office and lab areas. Rough-in of mechanical and electrical systems is ongoing. Exterior wall system framing is complete. The remaining temporary weather enclosure on the north has been removed. Installation of the exterior enclosure, primarily masonry and glazing work, is concentrated on the north and west walls during the week. Storm drains along the south and east will continue. Work continues on the south retaining walls. Concrete paving/curb and gutter on the south will begin this week. Interior painting has begun, followed by floor finishing. Minor utility work will be ongoing. Expect congestion from delivery trucks, and take extreme care when walking around trucks waiting in the street.

West War Memorial Stadium (scheduled completion July 31) -- Installation of stair risers along with new slip-resistant coating is complete. The east War Memorial Stadium lower walk surface also is complete. Punch-list work is scheduled for this week.

UW Office Annex (21st Street and Garfield, scheduled completion Sept. 30) -- The project involves partial renovation of the lower level of the west wing for improvements to offices and other adjacent multi-use spaces. Demolition is completed, and interior wall framing is under way. Asbestos abatement is completed in the conference rooms and adjacent corridors.

University of Wyoming/Casper College Student Union (UW/CC Student Union, scheduled completion November 2013) -- Construction has started with site preparation and foundation systems. Structural steel frame is under way, and interior concrete stair towers are completed.

The UW Physical Plant reports the following activities for the week. Please direct questions to the service desk, 766-6225.

Steam Shutdown -- The annual campus steam shutdown is scheduled for July 20. A temporary boiler has been placed on the sidewalk northwest of the Washakie Center and will remain in place until Aug. 21. Tunnel doors will be open and barricaded for air flow. Please use extra caution around fan barricades.  

Corbett P.E. Building -- The pool will be closed for annual maintenance from July 22-Aug. 27.

Foundation House -- Louver/damper for attic ventilation is scheduled to be installed. Please use caution in the area.

Fine Arts (Crane Dance Studio) -- Due to flooding, the dance studio is closed until further notice. Excavation has begun on the northwest side of the building. Please use caution around equipment in this area.

Rochelle Athletic Center -- Construction will begin for the hydrotherapy pool room renovation in the football locker room. Access to the area will be limited to authorized personnel.

Campus -- New sod is scheduled to be placed at various locations around campus. Sprinklers will apply additional water to ensure successful transplant of new turf.

Knight Hall -- Renovations in the Registrar’s Office are scheduled for July 24-Aug. 14. Storage pods will be placed in the parking area north of Knight Hall and on the sidewalk to the west of the building. Please be aware of moving activities in this area.

Central Energy Plant -- The fenced construction area will remain through Aug. 20, the end of steam shutdown. The sidewalk adjacent to 19th Street remains closed to pedestrian traffic. Please use the sidewalk on the east side of 19th Street.

Prexy’s Pasture -- Exterior lights may be off around Prexy’s Pasture due to construction of the Sullivan Plaza in front of the Education Building and an underground bore in the area of Cheney Plaza.

Jacoby Golf Course -- Construction continues on the east campus drainage project at Jacoby Golf Course. Inlet work will begin and traffic on Grays Gable will be routed accordingly. Installation of sod at Pond #1 will necessitate the frequent application of additional water. Signs are posted at the affected holes and in the clubhouse. The affected holes will be off limits during construction hours (7 a.m.-5 p.m.) for the remainder of the construction period. Please use caution in the work areas.

College of Law Building -- Lighting replacements are ongoing in the Law Library. This project will help UW in its continued effort to be more energy efficient. The work is funded, in part, by energy rebates from Rocky Mountain Power. The student lounge area is currently undergoing a remodel. Please use caution around the work area.

Knight Hall -- The lighting replacement project will continue when additional materials arrive. Electricians will coordinate schedules with building occupants. This project will help UW in its continued effort to be more energy efficient. The work is funded, in part, by energy rebates from Rocky Mountain Power. Please use caution around work areas.

Law Library -- The high-density mobile storage project is ongoing in the basement. Shelving assembly is nearly complete. Book and microfiche moving will occur.

Honors Center (10th and Ivinson Streets) -- Painting and trim work are ongoing inside. Construction of the addition continues outside. Sidewalks around the house are closed. Please use alternate routes.

Wyoming State Vet Lab -- Landscaping work will be ongoing in front of the round building and by the main entry sign to the site. New signage is scheduled to be placed at the main entry and the LREC Lab Animal Facility. Please use caution in the work area near the driveway.

Biological Sciences Basement -- Cabinet installation is ongoing. Floor tile and carpet installation is complete. Please use caution around the construction area.

Sigma Phi Epsilon -- Brick replacement will continue as materials arrive. Please avoid deck area and use caution around equipment. 

Concrete Repairs -- No repairs scheduled for this week.

East Shuttle Lot (30th Street and Willet Drive) -- This project is complete.