Campus Construction Update for June 2

May 31, 2013
Construction workers
A construction staging area has been established on the south side of the Biological Sciences Building. (UW Photo)

These are among the construction activities scheduled June 2-8 at the University of Wyoming:

Electrical Outages -- Areas of campus will be without power intermittently for electrical switch cleaning. Sensitive electronic equipment should be powered down before the outage. Expect power outages in the following areas. Building contacts have been notified:

Saturday, June 1 -- Arts & Sciences and Biological Sciences buildings, 7-9 a.m.; Old Main, Aven Nelson and Williams Conservatory, 9:30-11:30 a.m.; Merica Hall, 12:30-2 p.m.; Student Health and Hoyt Hall, 2-3:30 p.m.; Ross Hall, 3:30-5 p.m.

Thursday, June 6 -- Half Acre Gym, 5-7 p.m.

The UW Facilities Planning Office reports the following activities for the week:

Education Annex – Literacy Research Center and Clinic (lower floor, Education Annex; scheduled completion January 2014) -- The lower (first) floor of the Education Annex is closed for construction. Construction activities will begin this week with establishment of construction and staging areas. Access to the alleyway and related parking east and south of the Agriculture Building will be closed, and temporary access/egress detour will be established west of the Agriculture Building. Pedestrian sidewalk in the Ed Annex vicinity will be closed on the south side of Lewis Street, with pedestrian access rerouted to the north side of the street upon establishment of the construction limits. Parking in the Ed Annex vicinity will also be closed on the south side of Lewis Street upon establishment of the construction limits. Pre-demolition activities, including waste removal-related traffic, may also be occurring. Please observe all posted traffic control and construction signage.

Biological Sciences Building Mechanical Modifications (Scheduled completion mid-August) -- The building’s mechanical system will be extensively modified over the next several months. The contractor has started the major portion of the work. Staging is established on the south side of the building (with no pedestrian access) and in part of the Ivinson Parking Area. Traffic will be rerouted along the east side of Biological Sciences. Building users are encouraged to use the northwest entrance to avoid construction activities. Asbestos abatement continues on the upper floors. New ductwork is being installed on the first floor, and preparation for steel installation on the roof is in progress.

Buchanan Center for the Performing Arts (Fine Arts Building, renovation and expansion, scheduled completion December 2014) -- Additional project information is available here. The parking lot on the east side of the UW Performing Arts Center is closed. It is being used for construction staging and will be converted into a green area following construction. Building visitors should use the lot on the north side of the building. Those entering the Performing Arts Center must now enter through the doors on the west side of the building. This will be the entrance for all building operations, including classes, ticket purchases and performances, until construction is complete. The east side of the Fine Arts Building is a secured construction zone with restricted access. The deconstruction and excavation earthwork continues. Underground utility work is complete for this phase of work. Heavy truck traffic will be frequent near the College of Law and on Willett Drive.

White Hall Renovations -- New installations continue on the basement through second floors. Window replacement is complete. Punch-list items are complete on the fourth through 12th floors. Re-roofing activities have begun, with more truck traffic on the south side of the building. The new east entry metal framing is complete, and work is starting on the exterior wall and roof finish. Fencing is placed around the area. The west parking lot will be closed until late summer.

Marian H. Rochelle Gateway Center (22nd and Grand, scheduled completion fall 2014) -- Additional project information is available here. Site excavation and site utility work, and concrete foundation work, is under way. The vertical concrete structural sheer walls and the 60-foot-tall concrete shaft walls for the elevators are being constructed. All of this type of site work will continue through May.

University of Wyoming/Casper College Student Union (UW/CC Student Union, scheduled completion November 2013) -- The primary building enclosure is complete, allowing interior construction activities to proceed on or ahead of schedule. Rough-in construction is generally complete throughout UW/CC third- and fourth-floor spaces, and preliminary finish construction has started. Overall project construction is approximately 80 percent complete.

Education Annex Canopy (Scheduled completion August 2013) -- Construction activities have begun on the project, including the erection of fencing and temporary barricades defining the construction and staging areas. Vehicular access and parking availability in the lot north of the Education Building will be limited throughout construction and will be subject to frequent revision as construction activities dictate. During construction, pedestrian access to the north entrance of the Education Building and the east entrance of the Education Annex will be maintained. However, ongoing construction activities will require access to be limited to designated pathways. Pedestrians and motorists should exercise caution in the area.

Half Acre Gymnasium Addition and Renovation (Scheduled completion spring 2015) -- Full project information is available at www.uwyo.edu/ha-renovation. Half Acre Gymnasium remains open and accessible via the west entrance. Pre-construction activity at the project site will continue this week. Phase I, consisting of the demolition and reconstruction of the east portion of the existing building, continues with the establishment of construction and staging areas north, south and east of the building. Temporary staging also may be defined near the west entrance as required by the ongoing construction-related tasks. The day lot parking area and roadway immediately east of Half Acre Gymnasium are closed. Temporary day-use parking will be established in the lot east of the Wyoming Union. Please use caution in the vicinity of Half Acre Gymnasium, as pre-construction activities continue.

Enzi STEM Facility (Lewis Street between 10th and 11th streets, scheduled completion June 2015) -- Workers are waiting for the asphalt plant to fire up before patching streets.

ESCo Project (Energy Services Company) -- Long Energy Services Co. employees and contractors will continue to work on lighting retrofits in the Engineering and Agriculture buildings, which will impact building occupants. Workers will wear identifying badges.

Orr Hall Apartment Renovation and Window Replacement -- Apartment demolition work has begun and will continue over the next few weeks. Window replacement has started on the 12th floor and will continue down each floor. The contractor staging is on the south side of Orr Hall.

Energy Innovation Center (formerly ERC, at 1020 Lewis St.) -- Lewis Street remains closed during construction. The School of Energy Resources and Enhanced Oil Recovery Institute are now located in the EIC. First-, second- and third-floor labs are being occupied. Access to main campus now includes the passage between Engineering and the new EIC, along with access between Earth Sciences and the Berry Center. Access to the EIC north entrance will be from the east along Lewis. Parking will be limited in areas around construction. Audio-visual systems and 3-D visualization systems are installed, with operational testing under way. Congestion and traffic on Lewis continues due to street closure and ongoing construction. Watch for UW and contractors’ trucks and equipment.

The UW Physical Plant reports the following activities for the week. Please direct questions to the service desk, 766-6225.

General Storage -- The contractor will begin mobilization and site preparation the week of June 3. Shipping and Receiving will be operational in the same location throughout the duration of the project. Completion of the project is scheduled for November 2013. Please use caution around the construction area.

Centennial Complex (American Heritage Center and art Museum) -- Roof replacement operations will begin. Crews will set scaffolding on the cone portion of the building, which will be in place until November. The stair entry will be closed for several days during scaffold replacement. Elevator access will remain open. Roof drain re-sets will take place in the Art Museum offices and archives storage area. Staging area will be placed on the north side of the building. Use caution in work areas.

Health Sciences Building -- Maintenance of the air handling will be ongoing throughout the week of June 3 and will be shut down periodically. Room temperatures may fluctuate. The cadaver and animal labs will not be affected. Building contacts have been notified.

Old Main/Arts & Sciences -- Weecycle Environmental Consulting will sample non-destructive lead base paint in the Arts & Sciences Building June 3-7. Sampling of Old Main is complete.

Union Copy Center -- Remodeling of the Copy Center will be ongoing throughout June. Copy Center equipment will be secured in an enclosed area outside of the entrance and will remain open during renovations. Use caution in the area.

Performing Arts/College of Law Building -- Parking lot striping will occur around the pump house this week. Please use caution around painting crews and equipment.

Crane Hall -- Striping of the east parking lot will occur this week. Use caution around painting crews and equipment.

College of Agriculture Building -- Moving of the wind tunnel to the Lutz Building will begin this week. The driving lane between the Education Annex and the Agriculture Building will be the center of the move. Expect periodic closures in this area. Please use caution around moving equipment.

Early Child Care Center -- Work is scheduled to begin this week to install a new concrete ramp, and the southwest sidewalk will be closed. Please use caution in the area.

Landmark Apartments -- Roof replacement and attic upgrades will continue on the 12-unit complex. Crews will begin with units 445-452 and move to 453-460. Please use caution around equipment, barricaded work zones and fenced staging areas. Project completion date is Friday, Aug. 16.

Campus -- Crews continue to activate irrigation sprinkler systems for the summer season. Overspray onto sidewalks and driveways could create slippery areas. Weed spraying is ongoing, weather dependent.

Landmark and Spanish Walk Apartments -- Weather permitting, utility potholing, trenching and conduit installation will continue this week. Heavy equipment will be in the area, and sidewalk closures are possible. Use caution around heavy equipment and crews. This project will continue through May.

West Campus Electrical Relocation -- Potholing for utilities, excavation and horizontal drilling in the area of 9th-11th/Lewis-Flint streets will continue. Heavy equipment will be in the area. Partial sidewalk and street closures are possible.

Old Main -- Reconstruction of the men’s fourth-floor restroom will continue this week, and it will remain closed until complete. Please use caution around crews and equipment in the area.

Ross Hall Cafe -- Ross Hall Cafe renovations continue. The facility will be closed through the summer and is scheduled to reopen for the fall semester. The contractor staging and parking area will be on the north side of the building. Use caution in the area.

Cooper House -- Painting will continue throughout the building this week. Use caution around crews and materials.

Geology Building -- Renovations to Classroom 216 are ongoing. Use caution around crews and equipment in this area.

Union Parking Lot -- Striping operations are complete.

Earth Sciences Building -- Painting in the hallways is complete.

Find us on Instagram (Link opens a new window)Find us on Facebook (Link opens a new window)Find us on Twitter (Link opens a new window)Find us on LinkedIn (Link opens a new window)Find us on YouTube (Link opens a new window)