Campus Construction Update for June 17

(Note: The weekly construction update highlights only projects with new developments. Comprehensive updates are distributed monthly. For the most recent comprehensive update, click here.)

These are among the construction activities scheduled June 17-23 at the University of Wyoming:

Core Campus Steam Shutdown (UW Operations) -- The annual campus steam shutdown will begin at noon Monday, July 16, and will continue through Aug. 20. Most campus buildings between 22nd and Ninth streets, and Ivinson and Lewis streets will not have hot water or steam during the shutdown. A portable boiler will be placed near the Washakie Dining Hall during the week of July 9 and remain on-site until Aug. 20.

Campus Irrigation (UW Operations) -- Crews will begin turning on irrigation systems throughout campus. Use caution, as some sidewalks could become slick. Please excuse the inconvenience of detours walking around campus.

Old Main (Marshall Contracting; June 2018) -- Renovations will begin in June to the President’s Suite, converting two bathroom sections into one, as well as painting, new carpet and renovations to the boardroom. Please be aware of work crews in the building.

Physical Sciences Building (MSI; May 29-Aug. 20) -- The area between the Physical Sciences and Health Sciences buildings will be closed for storm sewer work. Please be cautious around equipment and crews. See attached map.

Classroom Building, Biological and Physical Sciences Buildings (MSI Inc.) -- The sidewalk east of the Classroom Building between Biological Sciences and Physical Sciences will be closed for a month due to the storm sewer renovations. See attached map

Knight Hall (Big Huhnks Excavation; May 22-July 4) -- Replacement of sod after the sewer repair will begin. Some concrete replacement also may occur. Please be cautious around these crews.

Mick and Susie McMurry High Altitude Performance Center (Construction manager at risk GE Johnson Construction Wyoming LLC, Jackson; June 2018) -- Within the existing facility, metal stud framing, drywall, mechanical, electrical and plumbing finishes are underway. All access to and egress from the Rochelle Athletics Center will be limited to the south entry doors. Construction of the north entry is underway. Traffic control, signs and barricades will be in place at the building interior and exterior during this process. Please use caution when near the project, and observe all construction signs.

Hoyt Hall West Parking (Big Huhnks Excavation; June 4-25) -- Parking west of Hoyt Hall will be closed. See attached map.

Physical Sciences Building (Colorado Hazard Control, Colo.) -- The abatement crews will be working in Lab 134 to abate and remove four research hoods June 22-23. The room will be contained to create negative pressure, and no one will be permitted to use the lab. Please use caution around the work area.

Lot Maintenance (UW Operations, Structural Trades) -- Weather permitting, summer lot maintenance work will run through August. UW shops will stripe lots and curbs, and replace signs as needed across campus. Sections of the lots may be barricaded during the day as needed for safety. Work will be finished for the Express Lot early the week of June 18 and then will start in the Sigma Phi Epsilon spaces on King Street. Please be cautious of crews and equipment in the area.

 

 

Contact Us

Institutional Communications
Bureau of Mines Building, Room 137
Laramie, WY 82071
Phone: (307) 766-2929
Email: cbaldwin@uwyo.edu


Find us on Facebook (Link opens a new window) Find us on Twitter (Link opens a new window)