This is an O&M Cost Input Screen with the following additional inputs for the Lime Spray Dryer SO2 control system at the top of the screen:
•Bulk Reagent Storage Time: This is the number of days of bulk storage of reagent. This factor is used to determine the inventory capital cost.
•Lime Cost: This is the unit cost of Lime for the Lime Spray Dryer system. It is shown here for reference and may be set on the Overall Plant O&M Cost screen.
•Waste Disposal Cost: This is the sludge disposal cost for the Lime Spray Dryer system.