IECM 12.0 beta User Manual > Modules Included with the IECM > Pulverized Coal (PC) Plant > SET PARAMETERS > CO2 Capture, Transport & Storage > 1. Membrane System > Retrofit or Adjustment Factors |
|
See Retrofit or Adjustment Factor Inputs for an explanation of retrofit costs. We do not recommend using the 2-Step w/ Air Sweep or NETL 2-Step w/ Sweep configurations for retrofit analysis. The membrane system has the following capital cost process areas:
•Membrane Module: (Not shown for NETL 2-Step w/ Sweep) This is the direct cost of the membrane module.
•Membrane Frame: (Not shown for NETL 2-Step w/ Sweep) This is the direct cost of the membrane frame structure.
•Compressors: (Only shown for 2-Stage Cascade) This is the direct cost of the feed-side compressors.
•Expander: (Only shown for 2-Stage Cascade) This is the direct cost of the expander.
•Vacuum Pumps: (Not shown for NETL 2-Step w/ Sweep) This is the direct cost of the permeate-side vacuum pumps.
•Heat Exchangers: (Only shown for 2-Stage Cascade) This is the direct cost of the heat exchangers.
•CO2 Drying and Compression Unit: (Only shown for 2-Stage Cascade) CO2 is dried and compressed to liquid form for transport over long distances.
•CO2 Cryogenic Purification Unit: (Only shown for 2-Step w/ Air Sweep) The CPU purifies, dries and compresses the CO2.
•CO2 Removal System: (Only shown for NETL 2-Step w/ Sweep) This is the direct cost of the CO2 removal system.
•CO2 Compression: (Only shown for NETL 2-Step w/ Sweep) This is the direct cost of the CO2 compression system.