The parameters on the O&M Cost parameter screen define the operating and maintenance cost assumptions used to estimate the cost of hydrogen pipeline transport. The following parameters are available:

•Electricity Price: This is the price of electricity used for compressor operation.

•Pipeline

•Labor Cost: This is the annual labor cost associated with pipeline operation and maintenance.

•Insurance (% CAPEX pipeline): This is the annual insurance cost expressed as a percentage of pipeline capital cost.

•Property Tax (% CAPEX pipeline): This is the annual property tax expressed as a percentage of pipeline capital cost.

•Licensing & Permitting (% CAPEX pipeline): This is the annual licensing and permitting cost expressed as a percentage of pipeline capital cost.

•Operating Maint & Repairs (% CAPEX pipeline): This is the annual operating, maintenance, and repair cost expressed as a percentage of pipeline capital cost.

•Compressor Station

•Labor Cost: This is the annual labor cost associated with compressor station operation and maintenance.

•Insurance (% CAPEX compressor): This is the annual insurance cost expressed as a percentage of compressor capital cost.

•Property Tax (% CAPEX compressor): This is the annual property tax expressed as a percentage of compressor’s capital cost.

•Licensing & Permitting (% CAPEX compressor): This is the annual licensing and permitting cost expressed as a percentage of compressor capital cost.

•Operating Maint & Repairs (% CMCC): This is the annual operating, maintenance, and repair cost expressed as a percentage of the compressor's initial investment cost.