Campus Construction Update for Feb. 3

February 1, 2013

These are among the construction activities scheduled Feb. 3-9 at the University of Wyoming.

The UW Facilities Planning Office reports the following activities for the week:

Performing Arts Center (Fine Arts, scheduled completion spring 2015) -- The contractor will fence off about one-fourth of the parking lot and set its trailers.

Enzi STEM Facility (Scheduled completion June 2015) -- Work will focus on installing water lines under 11th Street. Final completion on the sewer line is on hold until utility line conflict is resolved. 11th Street will remain closed between Lewis and Bradley streets. Watch for detour signs in the area. Lewis Street between 11th and 12th is open to limited traffic serving Engineering, Geological Survey, Earth Sciences and the Energy Innovation Center.

White Hall Renovations -- New installations continue on the sixth through 12th floors. Rough-in installations continue in the basement through fifth floor. Window replacement is complete on the ninth through 12th floors and will continue down each floor. The new east entry foundation is continuing. Fencing is placed around the area. The west parking lot will be closed until summer 2013.

University of Wyoming/Casper College Student Union (UW/CC Student Union, scheduled completion November 2013) -- The primary building enclosure is complete, allowing interior construction activities to proceed on schedule. Framing of interior partitions and mechanical/electrical rough-in continue throughout the UW third- and fourth-floor spaces. Overall project construction is approximately 61 percent complete.

ESCo Project (Energy Services Company) -- Long Energy Services Co. employees will be in a room TBD in Agriculture for a lighting mock-up, and in most of the Centennial Complex rooms this week for existing condition verifications. This will have minimal impact on occupants for short periods of time.

Energy Innovation Center (formerly ERC, at 1020 Lewis St.) -- Lewis Street remains closed during construction. School of Energy Resources and Enhanced Oil Recovery Institute personnel now occupy their third-floor offices. Access to main campus now includes the passage between Engineering and the new EIC along with access between or through Earth Sciences and the Berry Center. Access to the EIC north entrance will be on Lewis from the east along Lewis. Parking will be limited in areas around construction. Limited handicapped parking may be available south of the EIC and west of Engineering. Handicapped parking has been relocated to the northwest corner of Lewis and 10th streets, with access through the Berry Center or Earth Sciences Building to main campus.

Work on the third-floor lab and the second-floor conference rooms, along with 3-D visualization space, will be ongoing. The contractor has moved construction staging from the parking area north of Lewis. This will increase congestion and traffic on Lewis. Watch for UW trucks and equipment in addition to the contractors.

The UW Physical Plant reports the following activities for the week. Please direct questions to the service desk, 766-6225.

Snow Removal -- Physical Plant crews will remove snow as needed throughout the season. Watch for snow removal equipment, be careful and safe during snow events, and call the service desk at 766-6225 to report ice spots and problem areas.

Anthropology Building -- Due to investigation and repairs of a water leak on the first floor, access to the Lewis Street entrance may be closed intermittently for short periods while work is ongoing.  Please use the building’s west entrance when the Lewis Street entrance is barricaded. Exercise caution in work areas.

Alumni House, Classroom Building, Half-Acre Gym, Health Sciences, RMMC, Student Health/Cheney Center -- Installation of BEAP (Building Emergency Action Plan) plaques will be ongoing in these buildings.

Geology Building -- Renovations to Classroom 216 are ongoing. Please use caution around crews and equipment in this area.

Physical Science Building -- Modifications to the liquid nitrogen tank on the north side of the building are ongoing. Please use caution in this area.

Beta House -- Construction is substantially complete and punch list items are being completed. Video classrooms 105 and 205 are in use. HVAC controls work is nearing completion. New furnishings have been installed in most rooms used by the Outreach TV unit. Video editing equipment and media will be moved from the Centrex building beginning Feb. 12.

Rochelle Athletic Center -- Construction is ongoing on the hydrotherapy pool room renovation in the training room. The staging area is at the southeast corner of the building. Access to the area will be limited to authorized personnel.

Engineering Building -- Painting in the restrooms is complete.

History Building -- Painting operations are complete.

Knight Hall – Painting in the restrooms is complete.