Campus Construction Update for March 22

March 20, 2015

These are among the construction activities scheduled March 22-28 at the University of Wyoming:

Cowboy Field (Highland Landscaping, Laramie) -- The infield at Cowboy Field will be closed through May 15 to allow newly installed sod to properly take root. Please stay off of the infield grass. 

The UW Facilities Planning Office reports the following activities for the period:

Michael B. Enzi STEM Facility (General contractor AP Wyoming, Cheyenne; Lewis Street between 10th and 11th streets; scheduled completion May 2015) -- Please note that this project is being managed and administered by the State Construction Office. The intersection of 11th and Lewis is open for pedestrian and vehicle traffic. The sidewalk on the south side of Lewis is open, and there is access to the Earth Science/EIC loading dock. Street repair work will be limited to gravel fill until spring.

Construction activity continues throughout the building, with temporary enclosure being replaced with storefront and curtain wall to provide weather enclosure. Work in progress varies from floor to floor. Drywall finishing is proceeding ahead of painting on the first floor. Installation of ceiling grid has started. Laboratory casework is stocked throughout. Casework installation in underway on the first floor. Drywall work continues on the second floor ahead of painting. On the third floor, wall framing is nearly complete and drywall work is underway. Mechanical, electrical and plumbing rough-ins are progressing on the third floor ahead of the drywall. Installation of stairs and elevators continues. Steel trim-out, including the installation of the cornice at the top of the exterior walls, is progressing. There will continue to be numerous man lifts around the perimeter of the building, allowing work to progress on the exterior building skin ahead of the masonry installation. The mason will continue to work on several areas of the exterior as the sheathing (yellow board) and air barrier (gray rolled-on membrane) are completed. The mason is working in tented and heated scaffolding as needed to prevent freezing of the fresh mortar.

Final exterior wall system shell enclosure is proceeding on all sides, with sheathing and masonry work. Roof membrane work is complete. Flashing and trim-out of the roof is proceeding on the penthouse and lower roofs as weather permits. Installation of storefront and glass is proceeding on the west and east as weather and adjacent work permit. Curtain wall and glass installation is underway on the north and south as adjacent work and weather permit. Materials are stocked on site, with installation proceeding as glass is fabricated. Work on the atrium interior walls and detail continues in conjunction with the rough-in of mechanical and electrical systems. As masonry and glazing is completed on the east, preparation for site work will start.

Watch for construction traffic on Lewis, 10th, 11th and Bradley streets. For safety, pedestrians should make eye contact with equipment operators and delivery drivers outside the fenced area so they are aware of their presence. There will be equipment moving materials from storage to site, along with ongoing delivery of materials to site from vendors. You can visit the webcam here.

Buchanan Center for the Performing Arts (General contractor Sampson Construction, Cheyenne; Fine Arts Building renovation and expansion; scheduled completion May 2015) -- The parking lot on the east side of the Buchanan Center for the Performing Arts is closed and is being used for construction staging. Building visitors should use the parking lot on the north side of the building. Those entering the Performing Arts Center must now enter through the doors on the building’s west side. The northwest addition entry doors will open Monday, March 23.

The parking lot south of the Performing Arts Center will be partially closed on the east for storm sewer pipe installation. The northwest addition entry doors will be closed March 16-20 for a new concrete sidewalk and ADA ramp repairs.

Masonry stone work and exterior glazing are complete. Interior painting, flooring/wall tile, ceilings, electrical, plumbing and mechanical trim-out installations are ongoing in the majority of the north side addition. Interior framing/drywall/taping, painting, rough-in plumbing, duct work and electrical work are ongoing in the majority of the south side addition. High work in the Thrust Theater is complete, with lower framing ongoing. Controls wiring and programming are continuing. The box office has moved to a temporary location just southeast of the old box office location. The Department of Theatre and Dance northwest office addition is complete, and offices are now occupied. Punch lists are nearly complete. Work in the existing building is ongoing, with display boards, curtains, acoustic wall panels, AV and air balancing ongoing. Commissioning of existing building AV systems is complete, with deficiency reports issued. Heavy truck traffic will be frequent near War Memorial Fieldhouse, 22nd Street and Willett Drive, and along the road west of the College of Law Building.

Biological Sciences Building Mechanical Modifications (General contractor Independent Heating and Sheet Metal, Laramie) -- Roof installation is nearly complete, with final existing roof insulation repairs occurring on different days through the next three weeks. Staging at ground level will be on the southeast corner of the building. Exercise caution around the equipment and activities in the staging area.

Half Acre Gymnasium Addition and Renovation (General contractor Groathouse Construction Inc., Cody; Phase 1 east reconstruction/addition was substantially completed March 13; Phase 2, historic west renovation, summer 2015) -- Full project information is available here. Construction progress can be observed via the project webcam here.

Phase 1 of the Half Acre Recreation and Wellness Center was declared substantially complete on Friday, March 13, and opened on Monday, March 16. Punch-list tasks, building technology and transitional work toward commencement of Phase 2 renovation will continue post-occupancy. Access to Prexy’s Pasture from the east Wyoming Union parking lot between Half Acre and the Wyoming Union has reopened. Please observe temporary barricades, cautionary signage or other posted instructions in areas where work will continue post-occupancy.  

Phase 2 renovation of the historic western portion of Half Acre Gymnasium has begun upon the occupancy and opening of the Phase 1 addition. The historic west entrance of Half Acre Gymnasium is closed for the Phase 2 renovation. Additional construction and staging areas are being established on the west side of Half Acre Gymnasium and will result in increased congestion. Construction signage will be established as needed by specific site activities. Please observe all posted traffic control and construction signs in the affected areas. Completion of Phase 2 renovation is now scheduled for late summer 2015.

Construction and staging areas north, east and west of the existing building have been established and are closed to all vehicular and pedestrian traffic, except that which is construction related. Temporary day-use parking has been established in the lot east of the Wyoming Union. Pedestrian pathways north of Half Acre Gymnasium between Prexy’s Pasture and Willett Drive remain open; however, the continuing construction in this vicinity will result in increased congestion. Temporary traffic controls and signs will be established as needed by specific site activities. Please observe all posted traffic control, construction signs and temporary flagging in the affected areas.

The UW Physical Plant has 307 projects in progress valued at more than $42.6 million. Following is a list of ongoing construction activities in areas of campus that may impact you:

Snow Removal -- Physical Plant crews will remove snow as needed throughout the season. Watch for snow-removal equipment, be careful and safe during snow events, and call the Service Desk, 766-6225, to report ice spots and problem areas.

Downey/Orr/McIntyre Halls -- Elevator indicator lights are scheduled for replacement. Work is scheduled March 16-20 and will require intermittent closures of the elevators in each building.

Beta House (UW Physical Plant) -- Excavation is tentatively scheduled for the week of March 16-20 to locate and replace a broken sanitary sewer main. Work will occur on the west and south exterior of the building. Please use caution around moving equipment.

Engineering (UW Physical Plant) -- Ceiling tile replacement will occur March 13-20 in the corridors and all rooms of the Engineering addition. Please use caution around workers, ladders and damaged tiles staged for disposal.

Student Health (Colorado Hazard Control, Denver, March 2015) -- Abatement and replacement of the flooring in the first floor nurse’s station are nearing completion. Corridors may be closed intermittently during work. Please use caution around crews.

Lewis Street (Mechanical Systems Inc., Cheyenne, July 2015) -- Pipe installation continues in the Green Hill Cemetery. Work in vaults along Lewis Street from 11th to 15th streets also continues. Please be aware of temporary barricades, crews and vehicles in the area.

Buildings Affected by the Winter Closure Freeze -- (Physical Plant is undergoing a thorough review of the cause of each freeze-up, including the use of outside consultants, to help address future issues.)

-- Coe Library (History Addition) -- Reconstruction of the sixth-floor office is underway.

-- Jacoby Club House -- Physical Plant will complete restoration by March 31.

-- White Hall (Arcon Inc., Laramie) -- Insulated hatch replacement is ongoing. Relocation of the soffit louver is being evaluated by an outside structural engineer. Please use caution around work areas.

-- Downey Hall (Arcon Inc., Laramie) -- Replacement of insulation on the east end soffit is complete. Three additional insulated replacement soffit hatches are in the process of being installed. Please use caution around work areas.

Agriculture (UW Physical Plant, March 2015) -- The northwest stairway is being painted. Please use caution around the work area.

Education and Conference Center (Arcon Inc., Laramie, March 2015) -- A new security door is being installed to separate the conference center area from the main part of the Hilton. Framing of the entry door began March 18 and is expected to be complete by March 27.

Health Sciences/Pharmacy (UW Physical Plant, March 2015) -- Work will continue through March to renovate Room 483 to create three additional rooms. Installation of flooring began March 3. Installation of furniture was scheduled to begin March 11. Electrical, mechanical and plumbing work will be ongoing. Please use caution near work areas.

Geology/Earth Sciences (UW Information Technology; Trident Electric, Laramie, this month) -- Work is in progress on the east and west doorways to the atrium area. Please use caution near workers and equipment in this area.

Centennial Complex (Marshall Contracting, August 2015) -- Renovations are ongoing in the existing kitchen and dining areas on the first floor of the complex. These areas will be renovated to be used as a classroom and studio to support the Art Museum’s K-12 programs and other education initiatives. Construction is mostly contained within the existing kitchen and dining areas. Please use caution around crews and equipment in the area.

Knight Hall (Physical Plant and Arcon Inc., Laramie, February 2015) -- Construction of the ADA ramp is in progress. The base trim install and the remainder of the wood floor refinishing will be completed March 16-20. At that time, the corridor will be closed again and pedestrian detours will be posted. Please use caution around crews and equipment in the area.

Buchanan Center for the Performing Arts (Wheat Enterprises, Laramie) -- Potholing of the storm sewer located in the parking lot east of the Information Technology Building and across King Street near Crane Hall began March 16. Areas of “No Parking” will be indicated in the work area to allow crews access for utility locating. Please use caution in this area.

Wyoming Union (H&H Hardwoods, Laramie) -- Additional repair work in CJ’s and Rolling Mill began March 17. Stores will remain open. Please use caution around equipment and crews.

Education/McWhinnie Hall (Elk Ridge Builders, Laramie) -- Warranty repair of the sidewalk between the two buildings was scheduled March 16-20. The sidewalk may be closed at times, requiring use of alternate routes. Please use caution near crews and equipment.

Petroleum Engineering (Trident Electric, Laramie) -- Mechanical and control related upgrades were scheduled to be completed on the unit ventilators during the week of March 16-20.

Animal Science/Molecular Biology (Fremont Electric, Laramie, April 2015) -- LED retrofit kits will be installed in the existing lights throughout the building. Work is anticipated to take several weeks to complete.

Classroom Upgrades Project (Marshall Contracting, Spiegelberg Lumber & Building, Arcon Inc., Laramie, February 2015) -- Construction is underway in Wyoming Hall Rooms 204 and 434, Engineering Room 1044 and Ross Hall Rooms 108 and 109. Please be aware of crews and equipment in the area of these classrooms.

History (Arcon Inc., Laramie, June 2015) -- Renovations to the first-floor restroom and Rooms 57, 60, 152, 155 and 156 are scheduled to begin March 23. This work will necessitate the closure of the first-floor bathroom throughout the renovation. Please use caution near crews and equipment in the basement and first floor areas.

Visual Arts (GE Johnson) -- Demolition to selected portions of the building’s interior and exterior was scheduled to occur March 16-20. Use caution near crews and equipment.

Education Annex West Stairwell (General contractor Arcon Inc., Laramie, scheduled completion March 2015) -- The west stairwell will be remodeled to match the east stairwell, including an upgrade to energy-efficient lighting. Installation of the handrail is ongoing. The west stairwell will be closed except for emergency exiting. Please be aware of crews and equipment in the area.

Information Technology Center (Encore Electric, Englewood, Colo., June 2015) -- Improvements to the UPS System are ongoing. Work will be mainly above the ceiling space on the first floor, east side of the building. Local coordination will be via Jerome Lindsey. Please use caution near crews and equipment.

1217 Lewis St. Apartments (Summit Trucking and House Moving, May 2015) -- The apartments at 1217 Lewis St. are being deconstructed. To facilitate work, 13 parking spaces in the southeast-most part of the parking lot north of the Anthropology Building will be blocked off. Please use caution near this site.

Health Sciences Building (Stonehouse Inc., Laramie) -- All entryways to the Classroom Building and Health Sciences have been restored. Base preparation and concrete placement will begin when weather allows. Please use caution when exiting the Health Sciences Building on the southeast side. A temporary earthen walkway will be in place until concrete can be restored.

Contact Us

Institutional Communications

Bureau of Mines Building, Room 137

Laramie

Laramie, WY 82071

Phone: (307) 766-2929

Email: cbaldwin@uwyo.edu

Find us on Instagram (Link opens a new window)Find us on Facebook (Link opens a new window)Find us on Twitter (Link opens a new window)Find us on LinkedIn (Link opens a new window)Find us on YouTube (Link opens a new window)