Campus Construction Update for Aug. 27

(Note: The weekly construction update highlights only projects with new developments. Comprehensive updates are distributed monthly. For the most recent comprehensive update, click here.)

These are among the construction activities scheduled Aug. 27-Sept. 2 at the University of Wyoming:

Agriculture C and Engineering Addition Buildings (Summit Sealants, Montrose, Colo.; September 2017) -- Paint, caulk and minor repairs to the exteriors of Agriculture C and Engineering are ongoing. The Agriculture C west-end double-door entrance has scaffolding. Pedestrian traffic is routed through a scaffold passage tunnel to protect pedestrians from drop hazards from work occurring above. Please use caution around crews.

Cheyenne Family Medicine (Simon Contractors, Cheyenne; July 2017) -- Reconstruction of the north parking lot is ongoing. Work will require closure of the lot. Please use caution around work crews.

Spanish Walk Apartments (Arcon Inc. and Lance’s Painting, Laramie; August 2017) -- These buildings will undergo exterior renovation. Please use caution in the area. To ensure privacy, keep blinds closed.

Central Energy Plant (Arcon Inc., Laramie; October 2017) -- Demolition for the condensate tank replacement project is underway. Construction fence will be set up around the work area. The sidewalk on the west side of 19th Street will be closed, and 19th Street will be blocked occasionally. Please be cautious of crews and equipment in the area.

Engineering Education and Research Building (EERB) (Construction manager GE Johnson Construction Wyoming LLC, Casper; spring 2019) -- Structural steel erection is nearly complete. Concrete on the metal deck is being placed throughout the structure. Metal stud framing will start next week. Please steer clear of heavy equipment or delivery trucks parked on city streets. Click here to see a map showing revisions to bus routes and street closures. Please observe all construction signs.

Mick and Susie McMurry High Altitude Performance Center (Construction manager at risk GE Johnson Construction Wyoming LLC, Jackson; June 2018) -- The north side of the football field and the sidewalk to the north of the Rochelle Athletics Center will remain the only pedestrian paths from the east to the west across the north of the stadium until late August. Gates 6 and 8 will remain closed until the exterior site work and hardscapes are complete. All other pedestrian access routes are indicated by traffic-control barricades and signs. Site utility work, including the installation of steam lines and chilled water lines, is complete, with the exception of the final tie-in adjacent to the Visual Arts Building. Site flatwork is in progress, and barricades will be in place for new concrete pours. All pedestrian access will be rerouted when pours occur in the main pathways. Please use caution when near the project, and observe all construction signs.

The following project is complete:

Annual Steam System Shutdown (UW Operations) -- The annual campus steam shutdown was complete  Aug. 21, and heating systems were operational later that same day. 

 

 

Contact Us

Institutional Communications
Bureau of Mines Building, Room 137
Laramie, WY 82071
Phone: (307) 766-2929
Email: cbaldwin@uwyo.edu


Find us on Facebook (Link opens a new window) Find us on Twitter (Link opens a new window)