See Retrofit or Adjustment Factor Inputs for an explanation of retrofit costs. The pipeline transport system for all plant types has the following capital cost process areas:

Material Cost: This includes the cost of line pipe, pipe coatings, and cathodic protection.

Labor Costs: This covers the cost of labor during pipeline construction.

Right-of-way Cost: This is the cost of obtaining right-of-way for the pipeline. This cost not only includes compensating landowners for signing easement agreements but landowners may be also be paid for loss of certain uses of the land during and after construction, loss of any other resources, and any damage to property.

Booster Pump Cost: This is the total capital cost of a booster pump.

Miscellaneous Cost: This includes the costs of: surveying, engineering, supervision, contingencies, telecommunications equipment, freight, taxes, allowances for funds used during construction (AUFDC), administration and overheads, and regulatory filing fees.