The Capital Cost results of the syngas cleanup area are divided into two screens. This first screen, Capital Cost (BEC), presents the Bare Erected Cost (BEC) results. A single table displays the equipment included in the syngas cleanup area:

•Syngas Coolers: This is the BEC of all syngas coolers within the syngas cleanup area.

•Water Gas Shift Reactors: This is the BEC of the water gas shift reactors within the syngas cleanup area.

•MDEA Acid Gas Removal: This is the BEC of the MDEA acid gas removal system within the syngas cleanup area.

•Bare Erected Cost: This is the total of all technologies listed above. This result is highlighted in yellow.