IECM 12.0 beta User Manual > Modules Included with the IECM > Pulverized Coal (PC) Plant > SET PARAMETERS > SO2 Control > Wet FGD > Capital Cost |
|
This is a standard capital cost input screen.
If Bypass is enabled on the Config screen, an additional parameter appears before General Facilities Capital:
•Bypass Duct Cost Adder: (This is only available for technologies that support bypass.) The bypass capital costs are not specified with the other process areas. This parameter allows any direct capital costs incurred by the addition of bypass ducts to be added to the Flue Gas System process area. See the Retrofit screen for a list of the direct cost process areas.