IECM 12.0 beta User Manual > Modules Included with the IECM > Pulverized Coal (PC) Plant > GET RESULTS > NOx Control > 1. In-Furnace Controls > Capital Cost |
|
The Capital Cost screen displays a single table showing the capital costs related to the In-Furnace Controls NOx control technology.
Capital costs are typically expressed in either constant or current dollars for a specified year, as shown in the Status Bar. The following values are shown:
•Combustion NOx Capital Requirement: The total capital costs, including retrofit costs, for the LNB, OFA, and gas reburn technologies are included here. A zero is displayed when none of these technologies are installed.
•SNCR Capital Requirement: The total capital costs, including retrofit costs, for the SNCR technology is included here. A zero is displayed when an SNCR is not installed.
•Total Capital Requirement: Sum of the above. This result is highlighted in yellow.
•Effective TCR: The TCR of the retrofit NOx controls that is used in determining the total power plant cost. The effective TCR is determined by the % TCR Amortized on the Capital Cost input screen . This result is highlighted in yellow.
Copyright © 2023-2024 University of Wyoming. All rights reserved. Visit us at https://www.iecm-online.com/