The capital costs are divided into three screens. The third screen, Capital Cost (TASC), displays the Total Overnight Cost (TOC) and Total As Spent Cost (TASC) results for the entire plant in a single-table format:

•TPC w/ Regional Adjustment: This is the Total Plant Cost including the regional adjustment. This cost is the basis of the TOC estimation.

•Preproduction (Startup) Cost: This value is estimated as a percentage of the TPC, labor cost, maintenance material cost, consumables cost, and waste disposal cost. See SET PARAMETERS: Overall Plant: Capital Cost for details.

•Inventory (Working) Capital: This value is estimated as a percentage of the TPC and consumables cost. See SET PARAMETERS: Overall Plant: Capital Cost for details.

•Initial Cost for Catalyst & Chemicals: This value is estimated as the cost per unit of hydrogen product. See SET PARAMETERS: Overall Plant: Capital Cost for details.

•Other Owner's Cost: This value is estimated as the percentage of TPC. See SET PARAMETERS: Overall Plant: Capital Cost for details.

•Financing Cost: This value is estimated as the percentage of TPC. See SET PARAMETERS: Overall Plant: Capital Cost for details.

•Land: This value is estimated based on land size and unit land cost. See SET PARAMETERS: Overall Plant: Capital Cost for details.

•Total Overnight Cost: This is the total of all the components listed above. It is highlighted in yellow.

•Total As-Spent Cost: This is estimated based on the TOC and the TASC/TOC Multiplier specified on the SET PARAMETERS: Overall Plant: Capital Cost screen. It is highlighted in yellow.