IECM 14.0 beta User Manual > Modules Included with the IECM > Low-Carbon Hydrogen Production & Transport > GET RESULTS > Overall Plant > Fixed O&M Cost |
|
The Fixed O&M Cost screen shows the fixed O&M costs for the entire plant in a single-table format:
•Annual Operating Labor: Operating labor cost is based on the base wage rate, the number of operators per shift required to operate the plant per eight-hour shift, and the operating labor burden rate.
•Maintenance Labor: This parameter is estimated as a percentage of the TPC. See SET PARAMETERS: Overall Plant: O&M Cost for details.
•Maintenance Material: This parameter is estimated as a percentage of the TPC. See SET PARAMETERS: Overall Plant: O&M Cost for details.
•Administration & Support Labor: This parameter is estimated as a percentage of the Operating & Maintenance Labor aht the labor overhead charge. See SET PARAMETERS: Overall Plant: O&M Cost for details.
•Property Taxes & Insurance: This parameter is estimated as a percentage of the TPC. See SET PARAMETERS: Overall Plant: O&M Cost for details.
•Total Fixed O&M Cost: This is the total of all components listed above. It is highlighted in yellow.