Class Change Over: Reminder to avoid driving in Prexy's Pasture during class changeover. Pull over vehicle for duration of class changeover.
Physical Sciences Roll-Off Dumpster (April 16 - 23, 2024) - Starting April 16th there will be a roll-off dumpster placed at the NE corner of the Physical Sciences building. It will remain there for a week.
Annual Steam Shutdown (June 28 - August 6, 2024):
Our annual steam shutdown is scheduled for Friday, June 28th and will end Tuesday, August 6th.
General notes about the annual steam shutdown:
The portable boiler for the Washakie Complex will again be in place, so the complex will have domestic hot water for Downey, Orr, McIntyre & Washakie (installed week of June 17th).
Interactive Construction Map – The best quick reference for active capital construction projects, both vertical and civil can be found HERE. On the left side of the map, there are layers that you can select with the check boxes to change what is visible on the map. Click on the features on the map for information.
Vehicle Access to Core Campus - Vehicular traffic flow onto core campus will be restricted. Every effort must be made to keep vehicles off of the Prexy’s area during peak passing periods. The Berry Gate access, at 9 ½ Lewis street, will be the only access. Incoming vehicles must pass through this controlled entrance utilizing an authorized WyoOne card.
Information on Capital Construction Projects - Planning & Construction Website
Athletics Maintenance Facility (Shepard Construction Inc.; April, 2024) – The facility is being built to the south adjacent to the Indoor Tennis Complex. The two north outdoor tennis courts are closed. Utility rough-in activities in the new building are underway. A southern portion of the Little League Fields Parking Lot north of Armory Road is sectioned off for the project staging and materials laydown area. The area is outlined on the interactive construction map that can be found HERE. Use caution around work areas and watch for equipment traffic.
Aven Nelson Bldg. – Rocky Mtn Herbarium Expansion (Spring 2024) - Renovation of labs and offices on the 2nd Floor are underway, with completion scheduled for the end of Spring Semester 2024. Please use caution around construction activities, equipment, and materials.
Geology Building – Museum Exhibit Installation (Chase Studio, Inc., December 2024) - Preparations for the installation of the new Ancient Seas of Wyoming exhibit on the second floor of the Geology Museum are underway. Completion of the exhibit is scheduled for the end of the calendar year 2024. Please use caution around construction activities: crews, equipment, and materials.
Ivinson Parking Garage (Sampson Construction, December 5 - 12, 2023) - Sampson Construction will be polishing the concrete floors in Stair 1 (NW Corner of the Garage) on all levels of the stair and elevator lobby starting December 5 and completing on December 12, 2023. This will affect the stairway and elevator usage as well as the Handicap parking spaces on L-2 & L-3. Please use caution and obey signage in the affected areas.
Landmark Square Apartments and Early Child Care and Education Center (ECEC) Parking Lot Improvements (Simon Construction, May, 2024) – Simon Construction is removing and replacing the north & east parking lots of the Landmark Square Apartments. Please use caution in the area and watch for equipment. Construction scheduled to resume in Mid-May.
Law Remodel and Addition - Construction is in full Swing with FCI for the project.
Prexy’s Pasture Utility Work – WCEP Phase II (GE Johnson, Inc., Jackson, WY; Spring, 2024) – Utility work on the north of the transit stop on the east side of 9th St. is complete for the season, planting will take place in the spring, 2024. Work between Old Main and Biological Sciences is complete. Planting will take place in the spring, 2024. The communications directional boring and surface restoration is complete in the Merica parking lot area, landscape work will conclude in the spring, 2024. Preparation activities are currently underway for tunnel demolition and final distribution piping scheduled for late spring and summer. Detail, phasing, and logistics information will be available shortly.
Student Housing and Dining Project (JE Dunn Construction, Inc., Denver, CO; August, 2025) – Please review the map found here for site access and traffic logistics. Foundation activities and vertical structures on the north and south halls are in process. Please observe all detour signage and use caution around the active construction areas. Utility work at the 15th and Ivinson intersection will start 3/07. The intersection will not reopen until late summer, please observe all detour and closure signs.
Student Union and Prexy's Pasture (4/11/24 - 4/29/24) - Sewer drain installation will occur from 4/11 through 4/29/24 in the area around the Student Union in Prexy's Pasture. Please follow all barricades and signage in the work area.
University of Wyoming campus (United Building Specialty’s (UBS) & Crawford Insurance, April 15 - May 31, 2024) – UBS and Crawford insurance will be doing roof inspections on all of the University campus roofs. Please be aware there will be contractors on the roofs.
War Memorial Stadium West Stands Renovation (GE Johnson, Inc., Jackson, WY; January, 2026) – The south Fieldhouse (or east Corbett) parking lot and adjacent south and east sidewalks are closed. The west stands including the area underneath the west stands and east of the Fieldhouse are also closed for construction activities. Please review the map found HERE for site access and traffic/pedestrian detour routes to campus. Please observe all detour and construction signage including using caution in the area.