These are among the construction activities scheduled Nov. 21-27 at the University of Wyoming:
Campus Power Outage --
Sunday, Nov. 21, from 6 a.m.- 4 p.m., there will be a power outage on campus
between 15th and 9th Streets. All buildings on west campus - this includes all
of the buildings around Prexy's Pasture, Coe Library, Old Main, all of the
buildings along 9th Street, Ross and Knight Halls and others, will be without
power from about 6:30-7:30 a.m. while electric feeds are re-routed. Power will
then be restored to most buildings while work continues on the project.
Toward the end of the day,
another one-hour outage to all west campus buildings will be required to
re-route the electric feeds. This work is necessary to relocate two electrical
transformers as part of the Berry Center project. Building contacts have been
notified, backup generators arranged for critical loads, and arrangements made
as needed for special situations. Please avoid the work area around the Berry
Center project so the work can proceed smoothly and quickly, and use west
campus buildings on Sunday only if absolutely necessary.
The UW Facilities Planning Office reports the following activities scheduled for the week:
Energy Resources Center (1020 Lewis Street, former site of the old power plant) -- Site cleanup will take place with Berry Center contractor removing stored materials and equipment upon completion of the Berry Center. Fencing will be reconfigured to secure site.
Berry Biodiversity
Conservation Center (Faculty scheduled to move in during December, facility
will be open for spring semester) -- 9-1/2 alley is now open. Lewis Street
remains closed from 10-1/2 to 11th Streets for contractor staging area for the
ERC project. The following work and installations are scheduled to take place
next week:
All floors -- Punch list
work, cleaning and furniture installation, some congestion may be experienced
due to offloading of lab equipment and furniture.
Exterior: Vault relocation
and power shut down is scheduled for Sunday, Nov. 21, which will shut down the
9-1/2 alley and parts of Lewis Street for most of the day. The power will also
be off to the Berry Center and some surrounding buildings during this time.
UW Tennis Facility (Armory Road across from Little League Complex, scheduled completion: Feb. 15, 2011) -- Steel has arrived on the job site; columns will be erected during the week.
Downey Hall Renovation -- Door frames, fire protection and metal framing installation will continue at the interior. Framing the north entrance is also schedule to occur during the week.
Visual Arts Center (22nd Street and Willett Drive near the Centennial Complex, scheduled completion is late fall, 2011) -- Foundation work and new utility excavation will continue during the week with possible street work for utilities. Utilities relocation will continue along with some new utility work. Erection of steel will start this week and will continue into December. The masonry work will continue into December. Be aware that there will be additional truck traffic with delivery of structural steel in addition to frequent heavy construction traffic for delivery of materials throughout the week. Foot and vehicular traffic will not be permitted across the site. There may be extended workdays and, weather permitting, there may be work on weekend days.
Education Annex (Scheduled Completion: This fall) -- Access is open for scheduled classes. Installation of art design and related finish upgrades continues on the second and third floors. All major installations (aside from the feature wall) are complete. Feature wall installation is scheduled to begin the week of Dec. 13. Work continues on punch list items.
Summit View Apartment Deconstruction Phase II (South of Willett Drive between Crane and 22nd streets to Arrowhead) -- Deconstruction on the four blocks is nearly complete. The entire four blocks are fenced off, so pedestrian and vehicle traffic will need to go around the area. Abatement is complete and the deconstruction is nearly complete. Fencing is being placed east of Crane from Coe to Arrowhead for deconstruction of the two remaining blocks so pedestrian and vehicle traffic will need to go around this area also.
Biological Safety Lab, Level Three (BSL3) additions to the State Veterinary Laboratory -- Punch list items will be addressed and final testing of the mechanical system will begin.
Kendall House (Southeast corner of 8th and Fremont streets, is the new home of the Ruckelshaus Institute and Helga Otto Haub School of Environment and Natural Resources and the Wyoming Conservation Corps) -- Personnel have moved into the basement; and basement punch list items are complete.
The UW Physical Plant reports the following activities for the week:
College of Engineering Building -- Stair tread replacement continues at the main building entrance on the west side. Treads to the basement have been completed; first and second floor treads will be completed during the week. Please use the east stairway to access the basement.
South Shuttle Lot -- Two additional light poles have been erected in the gravel part of the lot, and this work is complete.
College of Agriculture Building -- Painting will continue in the fourth floor hallway next week. Please use caution around work areas. Work in the electrical rooms on the fifth and sixth floors is complete.
Coe Library -- Modification of the air handling system in the penthouse mechanical rooms of the old building continues. Painting of the southeast central stairway is complete.
Corbett P.E. Building -- Lights in the gymnasium are being replaced. Work will continue throughout November. Please use caution around this area.
Long-Term Parking Lot -- Work continues to install a utility conduit under the parking lot north of Willett and west of 30th Street. Please avoid the work area.
War Memorial Fieldhouse -- The lighting replacement project continues. Access to the infield is being coordinated with the athletics department.
State Vet Lab -- Removal of the chain link fence and other exterior objects around the round building is complete
Campus -- The house foundations at 9th and Grand, the east side of 13th Street between Lewis and Bradley, the southeast corner of 13th and Bradley and the southwest corner of 11th and Bradley will be will be filled and graded over the next several weeks as weather permits. The 11th and Bradley location is scheduled for next week. Parking will be affected and heavy equipment will be in use in these locations.
Campus -- Mechanical room surveys around core campus will continue for several more weeks. Surveys have been completed in Earth Sciences, Pharmacy, Hoyt Hall, Aven Nelson and Physical Sciences. Surveys will continue in Agriculture, Animal Science, Arts & Sciences, Biological Sciences, Classroom Building, Education, Engineering, Geology, History, Law School, and McWhinnie Hall. There should be no changes in normal building operations.
Snow Removal -- Snow and ice removal will occur as needed throughout the winter. Please use caution around snow removal equipment and be safe walking, riding and driving on the snow.
Please direct questions to the service desk, 766-6225.