Campus Construction Update for Jan. 18

January 16, 2015

These are among the construction activities scheduled Jan. 18-24 at the University of Wyoming.

Water Shutdown and Street Closure (General contractor Sampson Construction, Cheyenne; Fine Arts Building renovation and expansion) -- A water shut down will occur at the Corbett building Jan. 19 from 8 a.m.-noon. The parking lot south of the Performing Arts building will be partially closed on the east and west of Corbett next week for storm sewer pipe installation. This piping will go south, closing King Street Jan. 19-20. Use other routes to access UW buildings.

Fire Alarm Testing -- Annual fire alarm testing of campus facilities resumed Jan. 5. Intermittent alarms will sound throughout various building locations while devices are being tested. Schedules will be sent to building contacts for notification of test dates and times. Signs will be posted before testing takes place.

Snow Removal -- Physical Plant crews will remove snow as needed throughout the season. Watch for snow removal equipment, be careful and safe during snow events, and call the Service Desk, 766-6225, to report ice spots and problem areas.

Water Shutdown -- A water shutdown has been scheduled for Jan. 21, 6 a.m.-noon, for repairs to a fire suppression valve. Buildings affected will be the Education Annex, Engineering and Agriculture C. Building contacts have been notified.

Campus -- Replacement of light bulbs and lamps by Physical Plant crews throughout various building classrooms resumed Jan. 5. Work is scheduled to be ongoing through Jan. 23. Technicians will notify building contacts prior to work to avoid unnecessary interruptions.

Campus -- Jetting and cleaning of sanitary sewer mains located under King Street, Fraternity Row and Sorority Row will occur the week of Jan. 18. Vehicles and equipment could impede traffic flow at various times. Please use caution.

Buildings Affected by the Winter Closure Freeze -- (Physical Plant is undergoing a thorough review of the cause of each freeze-up, including the use of outside consultants, to help address future issues.)

-- Cheney International Center (Student Health) -- Restoration process is underway by Physical Plant through January.

-- Coe Library -- The first-floor reading room and the sixth-floor computer lab restoration process by Physical Plant will be underway through January.

-- Coe Library (History Addition) -- Hallways and Room 60 require ceiling work. A contractor (to be assigned) and Physical Plant will restore hallways.

-- Education Annex -- Belfor Inc. is completing demolition and drying, and will take the lead on restoration. There is no completion date established yet. The building is closed to the public at this time.

-- Jacoby Club House -- Drying and demolition is complete. Physical Plant will complete restoration by March 1.

-- State Veterinary Laboratory -- Restoration process is underway by Physical Plant through January. Long Technologies and Physical Plant will evaluate and make necessary repairs.

-- Visual Arts -- Restoration process is underway by Physical Plant through January.

-- Washakie Dining Center -- Restoration process is underway by Physical Plant, with completion scheduled Jan. 21.

-- White Hall -- Restoration process is underway by Physical Plant through January.

The UW Facilities Planning Office reports the following activities for the period:

Michael B. Enzi STEM Facility (General contractor AP Wyoming, Cheyenne; Lewis Street between 10th and 11th streets; scheduled completion May 2015) -- Please note that this project is being managed and administered by the State Construction Office. The intersection of 11th and Lewis is open for pedestrian and vehicle traffic. There will be minor utility work to complete steam line and stormwater work in the intersection of 11th and Lewis streets. With the arrival of winter, asphalt will not be available for patching, and street repair work will be limited to gravel fill to match the elevation of the adjacent asphalt.

Construction activity in the building continues as areas in the building are enclosed. Major structural steel work is complete. The crane will remain on site to facilitate lifting of mechanical, roofing materials and miscellaneous steel items including the fabricated stairs. Building enclosure is proceeding on the west, south and north with sheathing and masonry work. East and west roof work is complete. Roof work is proceeding on the penthouse and lower north and south roofs. Installation of storefront and glass is proceeding on the west as weather and adjacent work permit. Preparation for curtain wall and glass is underway. Installation of the curtain wall and glass may start as soon as next week. Materials are stocked on site, and installation is waiting for glass fabrication. Temporary enclosure is continuing on the west portion of the building to facilitate interior work as the exterior wall systems are being constructed. Construction of interior wall framing is continuing on all floors in conjunction with the rough-in of mechanical and electrical systems. Work on the atrium enclosure is underway. Watch for construction traffic on Lewis, 10th, 11th and Bradley streets. For safety, pedestrians should make eye contact with equipment operators and delivery drivers outside the fenced area so they are aware of their presence. There will be equipment moving materials from storage to site. You can visit the webcam here.

Half Acre Gymnasium Addition and Renovation (General contractor Groathouse Construction Inc., Cody; scheduled completion of Phase 1, east reconstruction/addition, March 2015; Phase 2, historic west renovation, spring 2015) -- Full project information is available here. Construction progress can be observed via the project webcam here. Half Acre Gymnasium remains open and accessible via the west entrance. The day lot parking area and roadway immediately east of Half Acre Gymnasium are closed. Temporary day-use parking has been established in the lot east of the Wyoming Union.

Construction and staging areas north, south and east of the existing building have been established and are closed to all vehicular and pedestrian traffic, except that which is construction related. Access to Prexy’s Pasture from the east Wyoming Union parking lot between Half Acre and the Wyoming Union is closed until further notice. Please use alternate routes through the Wyoming Union or between the Union and Coe Library. Heavy truck traffic, including construction materials transport, concrete trucks and other haulers, will be frequent on Willett Drive west of 15th Street and along the perimeter of the Wyoming Union parking lot. Temporary traffic controls and signs are either in place or will be established as needed by specific site activities.

Phase 1 east reconstruction/addition construction continues to proceed toward completion. Interior activities remains focused on finishes in all areas. Drywall finishing, specialty plaster, priming and painting, ceiling systems, tile and specialty flooring, casework and building specialties, and building systems work are progressing on all floors. Exterior building finish work -- primarily stone and brick masonry -- is nearing completion on the north elevation. Specialty building equipment, including climbing wall/pinnacle components, are in process toward final installation. Building HVAC and specialty systems are in varying stages of start-up, testing and verification.

Pedestrian pathways north of Half Acre Gymnasium between Prexy’s Pasture and Willett Drive remain open; however, the continuing construction in this vicinity will result in increased congestion. Willett Drive west of 15th Street and south of Wyoming Hall has reopened to normal traffic. Site improvement work along the south perimeter of Willett Drive will continue. Site improvement work will impact portions of the parking lot east of the Wyoming Union through early March. Normal vehicular access to the parking lot will remain open; however, construction work along the north perimeter of this lot will require some temporary detours in that area. Temporary traffic controls and signs will be established as needed by specific site activities. Please observe all posted traffic control, construction signs and temporary flagging in the affected areas.

Berry Biodiversity Conservation Center:

-- Spruce Court (General contractor Arcon Inc., Laramie) -- Deck portion of work is substantially complete.

-- Exhibits (Designer: Ozark Museum of Natural History, Cedar Creek, Mo.) -- Installation of museum-style exhibits throughout the building is scheduled to begin in February. Minor modifications required to accommodate the exhibits are underway within the building.

Buchanan Center for the Performing Arts (General contractor Sampson Construction, Cheyenne; Fine Arts Building renovation and expansion; scheduled completion March 2015) -- The parking lot on the east side of the Buchanan Center for the Performing Arts is closed and is being used for construction staging. Building visitors should use the parking lot on the north side of the building. Those entering the Performing Arts Center must now enter through the doors on the building’s west side. This will be the entrance for all building operations, including classes, ticket purchases and performances, until construction is complete.

The parking lot south of the Performing Arts building will be partially closed on the east and west of Corbett next week for storm sewer pipe installation. This piping will go south, closing King Street Jan. 19-20. Use other routes to access UW buildings. The work will also cause a water shutdown in the Corbett building Jan. 19. Masonry stone work is complete on the east and south sides. Exterior glazing will continue on the east side for the next two to three weeks. Interior framing/drywall/taping, rough-in plumbing, duct work and electrical work are ongoing on the south side of the addition. Interior painting, flooring/wall tile, ceiling grids, electrical trim out and plumbing trim out installations are ongoing in the north side of the addition. The box office has moved to a temporary location just southeast of the existing box office. The theater northwest office addition interior painting is complete, exterior glazing is ongoing, and exterior stair installation is complete. Punch lists have been issued. Move-in for the northwest addition is scheduled for Jan. 20. Work in the existing building is ongoing, with display boards, curtains, acoustic wall panels, AV and carpeting ongoing. Heavy truck traffic will be frequent near War Memorial Fieldhouse, 22nd Street and Willett Drive, and along the road west of the College of Law Building.

Biological Sciences Building Mechanical Modifications (General contractor Independent Heating and Sheet Metal, Laramie) -- Final roof installation is ongoing. Please be aware of hammer drilling noise occurring daily. Staging at ground level will be on the southeast corner of the building. Exercise caution around the equipment and activities in the staging area. Animals are moved back into the Vivarium.

ESCo Project (Long Energy Solutions, Casper) -- Engineering air distribution and control work are complete, with air/water balancing 90 percent complete. Exhaust upgrades are complete. Punch lists have been issued.

The UW Physical Plant has 305 projects in progress valued at more than $44.3 million. Following is a list of ongoing construction activities in areas of campus that may impact you:

Knight Hall (Physical Plant and Arcon, Inc., Laramie, February 2015) -- Demolition of office 146A will begin Jan. 20 so an ADA ramp can be constructed. Dust-control barriers will be installed, and access through the adjacent stairway will remain in place. Bike racks outside of the north hallway will be temporarily relocated during demolition. The north entryway will be accessible. Please use caution near crews and equipment.

Buchanan Center for the Performing Arts (Colorado Hazard Control LLC, Denver, and Voltech Electric, Laramie, January 2015) -- The main lobby is scheduled to reopen Jan. 19. The electrical contractor will be working to install ceiling lights. Operations are scheduled to be complete Jan. 30. Please use caution near crews and equipment.

Buchanan Center for the Performing Arts (Mighty Ducts, Cheyenne, January 2015) -- Cleaning of the ductwork and air-handling unit will occur throughout the building. Building occupants may notice periodic interruptions to air flow within the building. Please use caution near workers and equipment.

Physical Sciences (Mullen’s Heating, Laramie, January 2015) -- Energy-efficiency and air-quality upgrades to the air-handling units began Jan. 12. Building occupants may notice periodic interruptions to air flow within the building.

Physical Sciences – Crews will be changing filters in unit ventilators located in hallway ceiling spaces. This activity will create some dust. Please use caution around step ladders in hallways.

Engineering (Mullen’s Heating, Laramie, January 2015) -- Energy-efficiency and air-quality upgrades to the air-handling are scheduled to begin Jan. 20. Building occupants may notice periodic interruptions to air flow within the building.

Classroom Upgrades Project (Marshall Contracting, Spiegelberg Lumber & Building, Arcon Inc., Laramie, February 2015) -- Construction is underway on the first three classrooms to receive upgrades as part of this project. Work will be ongoing in Law School Room 191, Ross Hall Rooms 108/109 and Arts and Sciences Room 209. Please be aware of crews and equipment in the area of these classrooms.

Visual Arts (UW Physical Plant) -- Investigation of a cold draft will continue on the southwest end of the second floor. Please use caution near workers and equipment in this area. 

Pharmacy (UW Physical Plant, January 2015) -- Painting of restrooms on all floors is ongoing. Bathrooms will be closed during maintenance operations.   

Tennis Facility (Trident Electric, Laramie, December 2014) -- Installation of two exterior lights is ongoing. Construction crews will trench and erect two light poles on the west side of the building near the entrance. Please use caution near crews and equipment.

Education Annex West Stairwell (General Contractor, Arcon Inc., Laramie, scheduled completion Feb. 15, 2015) -- The west stairwell will be remodeled to match the east stairwell, including an upgrade to energy-efficient lighting. Painting is complete, and installation of the handrail is ongoing. The west stairwell will be closed except for emergency exiting. Please be aware of crews and equipment in the area.

Spanish Walk, River Village and Landmark Apartments (UW Physical Plant, January 2015) -- Maintenance work is ongoing in various buildings of the apartment complexes. Please use caution near crews and equipment.

Wyoming Union (UW Physical Plant, January 2015) -- Renovations to Rolling Mill Café will continue through January. Rolling Mill will be closed for the duration of the renovation. Please use caution near crews and equipment.

Student Health (Commercial Flooring, Cheyenne, January 2015) -- Flooring renovations began Dec. 22 and will continue through Jan. 23. Corridors may be closed for a short time. Please use caution around crews.

Information Technology Center (Encore Electric, Englewood, June 2015) -- Improvements to the UPS System are underway. Work will be mainly above the ceiling space on the first floor, east side of the building. Local coordination will be via Jerome Lindsey. Please use caution near crews and equipment.

1217 Lewis Street Apartments (Summit Trucking and House Moving, May 2015) -- The apartments at 1217 Lewis St. are being deconstructed. The top portion of the apartments will be moved off site, and the remaining foundation will be demolished in January. Final site clearing and leveling will follow in the upcoming months. Several parking spaces in the lot north of Anthropology will be closed Jan. 1-23. Please use caution near this site.

Lewis Street (Mechanical Systems Inc., Cheyenne, June 2015) -- Lewis Street will remain closed from 10th Street to 11th Street. Excavation work is suspended until spring. Portions of Lewis Street and the main drive in Greenhill Cemetery will be barricaded temporarily for ongoing work in vaults. 

Health Sciences Building (Stonehouse Inc., Laramie) -- All entryways to the Classroom Building and Health Sciences have been restored. Base prep and concrete placement will begin when weather allows. Please use caution when exiting the Health Sciences Building on the southeast side. A temporary earth walkway will be in place until concrete can be restored.

Health Sciences (UW Physical Plant, January 2015) -- Work will continue through January to renovate Room 483 to create three additional rooms. Construction of walls, electrical and plumbing work will be ongoing. Please use caution near work areas.

Engineering Building (General contractor Independent Heating and Sheet Metal, Laramie; scheduled completion December 2014) -- Air management and digital control upgrades to improve building efficiency are substantially complete. Hot water balance for the heating system is still in progress. This requires all control valves to be open, leaving some parts of the building hotter or colder than normal. Balancing is expected to be complete by Jan. 23. 

Grand Avenue (UW Physical Plant, December 2014) -- Lighting work will continue through early January as remediation from the street expansion project is completed.

Coe Library (Mullen’s Heating, Laramie, January 2015) -- Energy-efficiency and air-quality upgrades to the air-handling units are complete.

Wyoming Union -- Painting of handrails is complete.

Washakie Center (UW Physical Plant, January 2015) -- Work to replace two tunnel entrance doorways in the lower level of the Washakie Center is complete. A door replacement at White Hall is scheduled for summer 2015. 

Contact Us

Institutional Communications

Bureau of Mines Building, Room 137

Laramie

Laramie, WY 82071

Phone: (307) 766-2929

Email: cbaldwin@uwyo.edu

Find us on Instagram (Link opens a new window)Find us on Facebook (Link opens a new window)Find us on Twitter (Link opens a new window)Find us on LinkedIn (Link opens a new window)Find us on YouTube (Link opens a new window)