Construction Report

UW Operations

Campus Construction Update for Oct. 18-26

Campus Irrigation Systems (UW Operations) – UW Operations Plumbing Shop will be winterizing the campus irrigation system for the next several weeks, through the end of October. Please use caution or alternative route if possible, as sidewalks and drive areas could become slick or slippery when wet with the cooler temperatures. We appreciate your patience during this time.

Health Sciences Building-South Wing Fourth Floor, WWAMI Classroom (Arcon Inc., Laramie; fall 2018) -- Demolition and reconstruction will continue in the south wing of the fourth floor through November, with temporary impacts to additional spaces on the third and fourth floors. Painting is scheduled for the weeks of October 15th and 22nd.  Please be cautious, and observe all construction signs.

Irrigation Expansion (Triple A; August-December 2018) -- Crews will be boring under public roadways and trenching throughout campus. Some roadways will be closed during construction. Expect traffic delays and detours.

New - Knight Hall (UW Structural Shop) – The elevator will be out of service on Tuesday, October 23rd for flooring installation. The North building access to the elevator hallway will also be closed. If you need assistance accessing anything not on the first floor, please see the Dean of Students office in room 128, via the east entrance to the building. Please use caution around the work area and observe all signs and barricades.

Ross Hall (UW Operations Shops; November 2018) – Sink and countertop revisions of Ross Hall bathrooms will begin starting with the 4th floor and working down through the building. Building water outages will be scheduled intermittently as needed. Only one floor will be disrupted at a time. Please use restrooms on adjacent floors and use caution around crews in the area.

This project has been completed:

Office Annex (Commercial Flooring, Cheyenne, and Cowboy Moving and Storage, Laramie) - Main lobby floor and stairwell re-carpeted.

 

 


Share This Page:

Contact Us

UW Operations

1000 E. University Avenue

Dept. 3227

Laramie, WY 82071

Phone: (307) 766-6225

Fax: (307) 766-4040

Email: svsdesk@uwyo.edu

1000 E. University Ave. Laramie, WY 82071
UW Operators (307) 766-1121 | Contact Us | Download Adobe Reader

Twitter Icon Youtube Icon Instagram Icon Facebook Icon

Accreditation | Virtual Tour | Emergency Preparedness | Employment at UW | Gainful Employment | Privacy Policy | Harassment & Discrimination | Accessibility Accessibility information icon