Campus Construction Update for Dec. 6 - Dec. 19

Colder Weather Advisory (UW Operations) -- UW Operations asks building occupants to assist with ensuring buildings and facilities are safe and secure. Make sure all windows and doors are completely closed with windows latched at the end of each day, and report any doors or windows that you are unable to close and secure to the Service Desk (766-6225). 

Campus Snow Removal (UW Operations) -- Crews will remove snow as needed throughout the season. Watch for snow-removal equipment; be careful and safe during snow events. Call the Service Desk (766-6225) to report icy spots and problem areas. 

Arts & Sciences (UW Operations/Trident Electric) - Generator power is being routed to the west campus telecom node - Completed 

Aven Nelson (UW Operations, Summer 2019) – Electrical contractors will be working throughout Aven Nelson and Williams Conservatory to install a fire alarm system. 

Engineering (Marshall Contracting, Fall 2019) – Phase II remodeling of the Student Success Center (SSC) is underway. Phase II of the SSC remodel is expected to continue through the Fall semester. Please use caution near crews and equipment. 

Engineering (UW Operations/Trident Electric, January 2020) – Corridor lighting fixtures in the petroleum wing are scheduled to be replaced over winter break.  Sections of the corridor will be blocked off at this time for associated abatement. 

Berry (UW Operations/ Fremont Electric, December 2019) -  HID exterior lighting around the berry center is scheduled to be replaced with LED. 

Ross Hall (Colorado Hazard Control) – Ross Hall is currently undergoing floor repairs, cleaning, waxing, abatement and flooring replacements on first, second and third floors. Please be cautious in these areas. 

Ross Hall (UW Operations-Structural Shop) - Fourth floor west wing abatement and flooring replacement has started, it will be closed and continue through the end of December. Please use caution in this area. 

Science Initiative Building (SI) (Construction manager GE Johnson Construction Wyoming LLC, Jackson; Spring 2022) – Excavation and foundation activities are in process. Please continue to observe all restricted areas, and traffic control provisions. The north half of Lewis St. between 9th and 10th St. will be closed for the duration of the project for construction staging and field offices. 

West Campus Satellite Energy Plant (WCSEP) (Construction manager GE Johnson Construction Wyoming LLC, Jackson; Summer 2021) – Excavation and foundation activities are in process. The ADA parking spots on the west side of the Anthropology lot have been re-located to the south side of Lewis St. adjacent to the 12th St. intersection. Please observe all traffic control provisions. 

Wyoming Union (UW Controls, November 2019): Controls are being upgraded in a portion of the basement due to recent AHU replacement. Please use caution around crews and equipment.

Contact Us

UW Operations

1000 E. University Avenue

Dept. 3227

Laramie, WY 82071

Phone: (307) 766-6225

Fax: (307) 766-4040

Email: svsdesk@uwyo.edu

1000 E. University Ave. Laramie, WY 82071
UW Operators (307) 766-1121 | Contact Us | Download Adobe Reader

Accreditation | Virtual Tour | Emergency Preparedness | Employment at UW | Privacy Policy | Harassment & Discrimination | Accessibility Accessibility information icon