Phase 1 of the Lewis Street Corridor follows the vision defined in the Lewis Street Master Plan adopted in 2019. The plan establishes the framework for converting the existing Lewis Street vehicular roadway to a meaningful pedestrian corridor through the north side of campus. The Corridor will extend the character of Prexy’s Pasture onto the north side of campus tying together the diverse architectural styles creating a cohesive, pleasing, and functional pedestrian and bicycle experience. The plan was created in conjunction with the Campus Master Plan.
The project includes a significant utility relocation and coordination with the installation of heating and cooling lines routed from the new West Campus Satellite Energy Plant to Prexy’s Pasture.
Contractor: GE Johnson Construction, Jackson WY
Architect: Norris Design
Construction Schedule:
Phase 1 Construction Start: Spring 2021
Phase 1 Construction Complete: Fall 2022
Project Size: 5 acres
Project Budget: $5,000,000
Project History:
Exterior Design Approval – July 2019
Campus Impacts:
12th Street between Lewis and Bradley Streets will be permanently closed to private vehicles beginning in the summer of 2022.