This project focuses on the west side of the stadium. The renovation will aim to improve fan experience, with a host of new amenities and game-day enhancements. Enhancements include improved seating, wider rows, and improved concessions, restrooms, lighting and a new press box/media area.
Contractor: GE Johnson Construction Wyoming, LLC
Architect: Arete Design Group, Sheridan, WY
Construction Schedule:
-
Construction Start: Fall 2024
-
Construction Complete: Summer 2026
Project Size: 171,000 SF
Project Budget: $84,900,000